Metro Line LRT delayed again until Spring 2015, maybe, hopefully

The City held a press conference late this afternoon to provide an update on the Metro Line LRT extension to NAIT. They should have waited until February 2, because once again we learned that the opening of the new line has been delayed. The new target date is May 2015, more than a full year after the extension was originally slated to open.

2014-12-07 McEwan Station
MacEwan LRT Station in December 2014, photo by Darren Kirby

Today’s news release thanked Edmontonians for their patience and used much more careful language than previous delay announcements:

“Based on the most recent testing schedule provided by Thales Rail Signalling Solutions Inc., the City of Edmonton is cautiously optimistic the Metro Line LRT will open to public service in spring 2015.”

Cautiously optimistic is a long way from confident. The reason for the delay is the same thing we’ve heard since the project was first delayed – the contractor is having problems with the signaling system:

“Thales appreciates the patience of everyone in Edmonton as we work to complete the signaling system for the Metro Line,” says Thales Vice President Mario Peloquin. “We understand how important this essential transportation infrastructure is for the people of Edmonton, and we remain committed to delivering an outstanding product that is safe, efficient and reliable, and that will serve the city for generations to come.”

The signaling system is responsible for controlling train traffic. It tracks train movements and keeps them on schedule. Part of the challenge is that with the Metro Line, the City is changing the signaling system from a traditional fixed block system to a more modern communications-based train control system, or CBTC. It’s this new signaling system that will enable trains on the Metro and Capital lines to share the same tracks.

Even though construction completed on time and $90 million under budget, the Metro Line still isn’t open. The project has been delayed numerous times over the last year or so:

  • In September 2013, everything seemed on track for an April 2014 opening.
  • In December 2013, the opening was delayed a few months until Spring 2014.
  • In the Spring of 2014, the opening was further delayed until the end of the year. That schedule was reaffirmed over the summer.
  • In October 2014, the opening was delayed again, with February 2015 identified as the earliest possible date.
  • Now, in January 2015, the opening has been delayed until May 2015.

Needless to say, there’s very little confidence in the latest target date.

New Edmonton Arena Construction
MacEwan LRT Station next to the new downtown arena, September 2014

It was in October 2014 that Mayor Iveson called the delays “unacceptable” and asked the City Auditor to review how the project had been managed. Since then, the City has held back $20 million from the $55 million contract with Thales, and the auditor has been investigating.

Now the City says that the latest schedule from Thales would have the handover of the signaling system take place by March 23, 2015. If by some miracle Thales is actually able to meet that date, the City would need approximately 6 weeks to evaluate the system and complete staff training.

“We are very concerned with the ongoing delay of the Metro Line and will continue doing everything we can to hold Thales to their new schedule. Our goal remains the same: to open the Metro Line for safe, reliable public service as quickly as possible.”

On the Metro Line LRT site, the City has made available a slide deck and an FAQ, both in PDF.

metro line delayed

The FAQ tries to explain what has happened and attempts to provide some confidence that the City is providing “increased” project oversight to ensure it gets done. After the number of delays this project has experienced, you have to wonder if sticking with Thales is the right approach, but that’s what the City is doing:

“At present, our best option is to continue supporting Thales to deliver the signaling system. Our expectation is that Thales will meet its commitments. The City has strict project oversight to ensure they do so. If they fail to meet a milestone or if testing does not proceed according to schedule, the City will hold Thales to account.”

Let’s hope the sunk cost fallacy isn’t at play here.

The City says they are “tracking milestones on a daily basis” and have increased resources on the project. “We’re working diligently to help Thales deliver the signaling system by March 23, 2015.” The FAQ even says the City has explored the option of using people to manage train movements in an effort to get the new line open more quickly, but they ultimately decided that approach did not meet requirements for cost, safety, reliability, or efficiency.

Curiously, the final question in the FAQ is, “are you feeling badly about the delay, City of Edmonton?” Here’s the answer:

“Everyone involved with the Metro Line project regrets the delay of this exciting transportation project. We ask for your patience and hope you’ll continue to bear with us as we work towards bringing the Metro Line into service in spring 2015.”

So we’ll have to wait until late March before we can be sure the Spring 2015 opening is actually going to happen. In the meantime, we’d better make sure the same problems aren’t going to plague the Valley Line LRT extension.

Go underground for Edmonton’s newest coffee shops

It was a little disappointing to miss the opening of three new coffee shops last month, but on the other hand, it was nice to have new places to explore after we got back! In October, Transcend returned to downtown with a new location in the Mercer Warehouse, Credo added a second location on 124 Street, and after years in the making, Burrow opened in the Central LRT Station. I checked out all three locations last week.

Transcend Mercer

Transcend Mercer

Let’s start with Transcend Mercer. After the location on Jasper Avenue closed, I wasn’t sure if or when Transcend would be back downtown. It was pretty clear that if they did return, it would be at a smaller, more manageable location. While the new cafe in the basement of the building is smaller, it’s bigger than I was expecting! I’m not sure why but I envisioned something with either limited or no seating, but there’s actually lots of room to hang out at Transcend Mercer.

Transcend Mercer

I went for my usual – a vanilla latte – and looked around the cafe. There’s only one window, but the space is surprisingly bright, and I love the wood beams and ceiling. I understand they will be adding artwork around the room, so that’ll add even more color and visual interest. Speaking of color, the green counter, black wall, and brown accents definitely give you a “coffee” feeling!

I’m sure the new cafe will be frequented by everyone in the building, and it’s great to have another coffee shop on 104 Street. I’m also happy to once again be able to buy Transcend beans throughout the week! For more on Transcend Mercer, check out Cindy’s review here!

Credo Coffee on 124 Street

Credo Coffee on 124 Street

As you may know, Credo Coffee on 104 Street is my usual spot. It’s extremely close to home, has great coffee, and has wonderful service. The only downside is that because Credo is so popular, it can sometimes be difficult to find a seat. The new location on 124 Street is quite a bit bigger though, so hopefully that won’t be such an issue there!

Credo Coffee on 124 Street

The new cafe is located at 10350 124 Street in the new Limelight building (which is just down the block from Remedy Cafe). It can be a little difficult to see, given that there are no signs on the building except for a vinyl banner where Credo is located. They are the first tenant in the building, so I hope better signage is coming.

Credo Coffee on 124 Street

Inside is open and roomy, with lots of seating and also lots of bar space. Though Credo’s space is mostly below street level, there are lots of windows which means lots of natural light. Oddly there are a lot of power outlets up high (I guess for Christmas lights?) so you might need a long cord if you’re going to plug in a laptop (maybe they can add some outlets lower to the floor).

My favorite vanilla latte was as delicious as ever, and it didn’t take long to feel right at home. I know I won’t make it to this location as often as 104 Street, but it’s great to see another fantastic addition to 124 Street.

Burrow Central Station

Burrow Central Station

A coffee shop in an LRT station? Finally Edmonton’s cafe scene has gone underground! Burrow Central Station (part of the growing Elm Cafe family) is the perfect addition to our growing and increasingly popular transit system, and I hope it’s a sign of things to come. Again my expectations were exceeded – I anticipated finding Burrow tucked away behind one of the walls, but instead found it centrally located in the concourse. You can’t miss it, and now that it is there, I simply can’t remember what it looked like before. Burrow looks like it belongs, like it should have always been there.

Burrow Central Station

Burrow uses Four Barrel Coffee from San Francisco, which I had not tried before. I decided to stick with the usual on my first visit (ok, ok, and also my second and third visits) and ordered a vanilla latte. I was pleasantly surprised to see they make it with real vanilla bean instead of syrup! I will have to go try a simple brewed coffee one of these days. They have a rotating lunch menu with a grilled cheese sandwich too, also on my list to try.

There is no seating in the LRT concourse, but for grab and go it’s hard to beat Burrow. My office is right above in the Empire Building, so I foresee many, many visits in my future! Again, check out Cindy’s review here.

Have you been to these three new cafes? What did you think? If not, raise a paper cup as Omar says, and go check them out!

Why does the University of Alberta want to be part of the Galleria project?

“The University has long desired to establish a significant campus in downtown Edmonton.”

That’s the first thing the Edmonton Downtown Academic and Cultural Centre (Galleria) business case from April 2013 identifies under opportunities and benefits for the University of Alberta. It sounds plausible, given the ongoing interest in revitalizing downtown and the University’s desire to play a role in the larger Edmonton community. But is it really true?

Here’s what columnist Paula Simons wrote in November 2001:

“Officially, a downtown campus isn’t an option. I’ve spoken to U of A President Rod Fraser, to University Provost Doug Owram, and to Jim Mitchell, the university’s vice-president of facilities. They all tell me it would be too expensive to build downtown, much more than developing land they already own in Garneau or southwest Edmonton. They say it would be too hard to find suitable space for labs and large lecture theatres. They say students and staff would feel isolated from campus life and facilities. They say it’s not their mandate to save downtown, but to serve the best interests of the U of A.”

That was around the time that the University of Alberta’s Long Range Development Plan (LRDP) was being developed (approved in 2002). It provides “a planning framework to accommodate and to guide physical development on University lands during the next thirty years.” Though it focuses on land and facilities that the University already owns, it does deal explicitly with the idea of a downtown campus:

ualberta lrdp

Though the plan has been amended a few times over the years, notably to incorporate Augustana Campus and most recently to incorporate updated plans for South Campus, that section has never been changed. “South Campus will accommodate much of the growth of the University of Alberta for the next thirty years” is what the most recent amendment says.

Even in 2005, when the University announced plans to buy the Hudson’s Bay building, it was not seen as a first step toward a larger campus in downtown or a change to previous plans. New President Indira Samarasekera said “the University of Alberta is a contributor to business, arts, and other sectors,” adding “we have an obligation to the community that we take seriously, and a downtown presence will build on that.” A few years later at the official opening of Enterprise Square, she said “that the University has finally crossed the river and found a place in the heart of the city is very significant” but also admitted that “it initially scared the heck out of me; we took a leap of faith.”

It was with some surprise then that Provost and Vice President Academic Dr. Carl Amrhein posted the following on the University of Alberta’s blog yesterday:

“The Galleria project is more than much-needed space for the University of Alberta—it is consistent with the university’s vision of an urban, linear campus connected by LRT where students, faculty and members of the public move freely around the city to access world-class teaching and research experiences offered at Edmonton’s post-secondary institutions. Imagine the vibrancy that 5,000 art, design and music students, faculty and staff will bring to the downtown core. Imagine the potential when students and professional artists interact through linkages with the Winspear, Citadel and Art Gallery of Alberta. The creative energy will be palpable!”

That seems to contradict not only statements by earlier University officials, but also the LRDP. Had the need for “an integrated campus environment” changed? Had the disadvantages about paying rent changed? Did student leaders now find a downtown location desirable? I reached out to Dr. Amhrein for clarification.

“There’s a technical point,” he told me, “which is that the Long Range Development Plan is concerned with real estate that the university owns and controls.” Given that the U of A would be leasing space inside the new Galleria project, it wouldn’t necessarily contradict the plan. He recognized the larger point however, and said “the argument for integrated locations is ease of mobility and the ability to move people around in a certain amount of time.” That’s where the LRT comes in.

Bay/Enterprise Square
Bay/Enterprise Square LRT Station, photo by Christopher Cotrell

“The feature that made Enterprise Square imaginable was the LRT,” Dr. Amrhein told me. “It meant that it was no more difficult to get from HUB to Enterprise Square than it was to get from HUB to South Campus.” He said the U of A’s first question then about the Galleria project was, “is there an LRT stop?” As both Churchill LRT Station and MacEwan LRT Station are close, the goal of an “urban, linear campus connected by LRT” is achieved at the Galleria, according to Dr. Amrhein.

In his blog post, Dr. Amrhein reiterated the University of Alberta’s key requirement for the Galleria:

“Yes, the university has identified climate-controlled access to the Galleria from the LRT as critical for our students, faculty and staff, and the patrons of the performances at the Galleria theatres and concert halls. A pedway is one solution, but there are others.”

He sounded annoyed that the pedway had become such a touch point in discussions about the Galleria. “The pedway is not a deal-breaker for the University,” he told me. Only “climate-controlled access” is a requirement. When I asked him to suggest alternatives to a pedway that could meet that requirement, initially he dodged the question. But asked a second time, he suggested the position of the buildings could provide the required access, citing the Telus towers and their connection to the LRT as an example. “Clever positioning with a plus fifteen would achieve the same result,” he said, noting that the project architects would have to rethink their plans to make that happen.

Dr. Amrhein told me the University requires climate-controlled access for three reasons. The first is the need to move faculty, staff, and students around campus in short periods of time. “When it’s dark and cold, there’s a disincentive to move around the facilities,” he said. The second is safety, which Dr. Amrhein said has been “completely lost in the conversation.” He stressed the importance of safety, saying that pedways are “well-lit and heated, and very visible” and that they often include security features. “There’s a personal safety issue here.” The third is accessibility of the performance venues for the community.

AuroraCollege_jm258
Dr. Carl Amrhein, photo by James MacKenzie

Back to the central question – why does the University of Alberta want to be part of the Galleria project? To answer that, Dr. Amrhein brought up Mayor Mandel and his vision to have all of Edmonton’s post-secondary institutions integrated and connected by LRT. “Imagine a medical student at NAIT,” Dr. Amrhein said. “That student can move from the classrooms at NAIT to the labs at the Walter MacKenzie Health Sciences Centre because of the LRT.” Integration across institutions like that would “put Edmonton in a very small group” of cities, Dr. Amrhein said.

It’s clear that Dr. Amrhein views the University’s participation in the Galleria project as something that will help Edmonton as a whole. “I hope it goes ahead.”

Edmonton announces bid to host the 2022 Commonwealth Games

On Monday, the City of Edmonton announced it will bid to host the Commonwealth Games in 2022. Mayor Iveson had this to say about the news:

“Our city’s successful history as a great event host city started with the 1978 Commonwealth Games. Hosting the games in 2022 will demonstrate to the world how much Edmonton has evolved and reflect the Commonwealth Games Federation’s confidence in our city.”

As recently as a week ago, the Commonwealth Games Federation was concerned about a lack of interest in hosting future Games, potentially due to in-fighting and cost. No city had yet stepped forward, and cities that had previously expressed interest such as Singapore, Birmingham, and even London, all cancelled their plans. Then, at the last minute, Edmonton and Durban, South Africa, stepped forward.

Queen Elizabeth II 1978
Her Majesty Queen Elizabeth II and His Royal Highness the Duke of Edinburgh attend the Commonwealth Games in Edmonton in 1978

When Edmonton hosted the Games in 1978, they were the biggest to date. Forty-six countries participated, sending 1,474 athletes to compete in 128 events across 10 sports. When the Games take place later this year in Glasgow, more than 70 countries are expected to participate, with more than 4,300 athletes competing in nearly 300 events across 17 sports.

Where did this come from?

The announcement seemed to come out of nowhere, but the possibility of Edmonton hosting the Games actually came up in February 2012, shortly after Commonwealth Games Canada decided to pursue another bid. Here’s what Mayor Mandel said at the time:

“I think 1978 (the last Edmonton Games) was a watershed moment for the city, and 2022, almost 45 years later, it would be a nice re-coming out party.”

“It’s a chance to showcase Edmonton. We have great facilities in the city, so I don’t think there would be a huge capital investment with these games other than some expansion. We would obviously have to do some upgrades.”

Big cities bid on major events to diversify their economies, attract tourists, build their reputations, and engage their citizens. Though many cling to a small-town mentality, Edmonton is a big city. Big cities bid on big events.

The 1978 Commonwealth Games were widely viewed as a coming out party for Edmonton, introducing us to the world stage. The City’s 2004 Annual Report reiterated this view:

“The Commonwealth Games [brought] unprecedented attention Edmonton, marking it as a city of international prestige and importance.”

It’s not like Edmonton has been standing still since 1978 either. We followed the Commonwealth Games up with the 1983 Universiade Games. We have hosted World Cup qualifying matches, World Figure Skating Championships, the 2005 World Masters Games, and much more. Perhaps biggest of all, we hosted the 2001 World Championships in Athletics.

The next few years will be especially busy. This year Edmonton is hosting seven games during the FIFA U-20 Women’s World Cup Canada, and next year we’re hosting eleven games during the FIFA Women’s World Cup Canada. Off the pitch, Edmonton is hosting the 2015 and 2016 Canadian Track and Field Championships, the latter of which will serve as the Canadian Olympic Track and Field Trials for athletes looking to compete in the Summer Olympics in Brazil. It’s going to be an exciting few years for sports in our city!

Would the federal government support the bid?

Edmonton’s bid to host EXPO 2017 was brought to a halt in 2010 after the Government of Canada withdrew its support, citing the unknown future costs of security. Mayor Mandel felt the real reason was a lack of support for our city, saying that “when it comes to Edmonton’s growth and ambition, our federal government simply isn’t interested.” He singled out MP Rona Ambrose for failing to build the necessary support in Ottawa for Edmonton’s bid.

Edmonton EXPO 2017 Launch

Do we need federal support for this bid? Financially, it seems unlikely a successful event could be staged without support from the Government of Canada, despite City Manager Simon Farbrother’s optimism that the City and Province could support it themselves. The reality is that hosting the Games is a $1 billion proposition, based on recent costs. Security concerns would also likely be a federal issue.

Would the federal government support this bid? Sport Canada guidelines outline that the federal government can only support two Canadian bids for major games in any decade. It is widely expected that Quebec City will bid to host the Winter Olympics, so Edmonton would be counting on being the second major event host.

Halifax was hoping to bid for the 2014 Commonwealth Games, but they were forced to withdraw their bid over concerns with the budget. It was the first time Canada had withdrawn a bid for a Commonwealth Games event. Edmonton’s bid would need to be rock solid.

What does this mean for LRT?

One of the drivers behind Edmonton’s failed bid to host EXPO 2017 was infrastructure money expansion for LRT. Big events require big money, and it was hoped that part of staging a successful event would mean expanding the transit network. Many Edmontonians were quick to make the connection to LRT after Monday’s announcement too.

It’s true that Edmonton’s LRT first opened in 1978, just months before the Commonwealth Games. But that project is not what took the LRT from conception to reality, nor is it what funded the construction. From Ride of the Century:

“In truth, the visionary planning that laid the foundation for the LRT dated back to the decommissioning of the streetcars in 1951, but it took until the early 1960s for the rapid transit dream to take coherent shape in D.L. MacDonald’s Report on the Present Operating Conditions of the Edmonton Transit System With a View to Determining a Policy for The Future Operation of the System in 1961.”

When the LRT opened on April 22, 1978, at a cost of $64.9 million, it was 7.25 km long with five stations.

LRT

Edmonton hosted the 1978 Commonwealth Games from August 3 to 12. Edmonton Transit had been planning transportation for the Games for two years, even assembling a fleet of 724 buses from Edmonton, Calgary, and Red Deer rolling stock to help meet demand. Their planning paid off.

“Edmonton Transit conveyed almost two million spectators to events over the nine days of the Games, and on August 8, the LRT system set a ridership record of over 69,000 people.”

“The Games were a shining moment for the city, and Edmonton Transit had played its part well passing the gargantuan test with flying colours.”

Just as we needed to continue building LRT with or without EXPO 2017, we need to move forward with LRT expansion whether we host the Games or not. I’d hate to see us tie LRT expansion money to the bid. LRT is our top infrastructure priority, and this event should have no bearing on that.

What does this mean for other infrastructure?

Events like the Commonwealth Games typically leave a physical legacy of facilities in the cities that host them. New sports and recreation facilities built for the Games could serve Edmontonians for years to come.

It is expected that Commonwealth Stadium would once again serve as the venue for the opening and closing ceremonies. It has received numerous upgrades in recent years, and could still receive more. Other facilities that were built for the 1978 Games, like Kinsmen, would likely receive upgrades and could be used. Foote Field was recently upgraded, and a new velodrome adjacent to Peter Hemingway pool has already been in the works. Edmonton had bid to host the 2015 World University Games, and had included a list of facilities as part of that bid that never moved forward. Those plans would likely be dusted off if this bid is successful.

Who is the competition?

In 1978, Edmonton’s competition was Leeds in England, a city with a population of about 200,000 more at the time. Our competition for the 2022 Commonwealth Games is Durban, a South African city of nearly 600,000 in a much larger metro area home to more than 3.4 million people. South Africa has never hosted the Games before, so that likely gives them an edge.

Apparently Durban had previously considered a bid for the 2020 or 2024 Summer Olympics, which suggests to me they are hungry to host another major international event and will be stiff competition. Durban hosted matches in the 2003 ICC Cricket World Cup and was of course one of the host cities for the 2010 FIFA World Cup.

Canada has hosted the Games four times: 1930 in Hamilton, 1954 in Vancouver, 1978 in Edmonton, and 1994 in Victoria. Edinburgh and Auckland are the only cities to have hosted the Games more than once.

Can Edmonton win? City Manager Simon Farbrother is certainly confident:

“We will, yes. We don’t go into these things to come second. Let’s put it that way.”

What’s next?

The cost of bidding had previously been estimated to range from $8 million to $10 million. Edmonton and Durban will work to finalize their bids by March 2015. After that, members of the Commonwealth Games Federation will meet a General Assembly in Auckland, New Zealand to choose a winner on September 2, 2015.

An Edmonton delegation will be travelling to Glasgow this year as official observers to learn best practices. The City has apparently talked with Glasgow officials about the bidding process too.

The City of Edmonton has said it will continue discussions with the Province and will be looking to engage other stakeholders throughout the country to win their support. Of course, Edmontonians will also be invited to get involved, so look forward to those opportunities in the near future.

City Council approves a new transportation goal and outcomes for The Way Ahead

It’s no secret that LRT is City Council’s top infrastructure priority. They have repeatedly stressed the importance of expanding our LRT network, and scored a win recently with the Valley Line. LRT is part of a bigger transformation that Council hopes to realize, which is a shift away from the car-dominated transportation network we have today to a network that offers realistic choice through a range of travel options. At Wednesday’s City Council meeting, they approved a new goal for The Way We Move that makes this transformation clearer.

City Council Swearing In 2013-2017

In November last year, Edmonton’s new City Council took part in a series of strategic planning sessions. In addition to serving as a crash course on the City’s strategy and approach to long-term planning, the sessions were also a way to ensure the new Councillors were on board with the corporate outcomes, measures, and targets for each of the six 10-year goals identified in The Way Ahead. Among the key outcomes of those meetings were a desire by Council to review the goal statement for The Way We Move, as well as a desire to emphasize public engagement within The Ways.

The public engagement action is being handled through a new Council Initiative, and I think we’ll hear much more about that in the weeks ahead. I’m looking forward to it.

The goal for The Way We Move was reviewed and discussed at a couple of subsequent Council meetings, notably January 28 and March 11. Council wanted to stress the use of public transit, but they wanted to make it clear that Edmontonians would have choice. The goal they ultimately settled on reflects both of those desires and has led to a new set of outcomes too.

Current Goal: Shift Edmonton’s Transportation Mode

The current goal statement for The Way We Move is focused on “mode shift”, which is meant to convey that while the majority of Edmontonians get around the city using vehicles today, that should not always be the case. The reasons for needing a shift included changing our urban form to be more sustainable, accessibility, supporting active and healthy lifestyles, reducing the impact on the environment, and attracting business and talent to Edmonton.

Here’s the goal statement that accompanies the goal:

“Modes of transportation shift to “fit” Edmonton’s urban form and enhanced density while supporting the City’s planning, financial and environmental sustainability goals.”

Each goal also has an ‘elaboration’ associated with it. The current one for transportation reads:

“In shifting Edmonton’s transportation modes the City recognizes the importance of mobility shifts to contribute to the achievement of other related goals. To do so suggests the need to transform the mix of transport modes, with emphasis on road use for goods movement and transiting people and transit use for moving people. This goal reflects the need for a more integrated transportation network comprising of heavy rail, light rail, air and ground transport, and recognizes the important contribution that transportation makes to environmental goals.”

While the current wording attempts to connect with the other goals in The Way Ahead, it doesn’t as forcefully make the case for offering alternatives to single-occupant vehicles. The other challenge is that “mode shift” doesn’t mean anything to most of us, and sounds bureaucratic.

Perhaps more importantly, this was the only goal that was presented as if was worth doing solely to achieve the other goals. Surely a shift in how we move around the city should have benefits of its own!

New Goal: Enhance use of public transit and active modes of transportation

The new goal statement reads:

“Enhancing public transit and other alternatives to single-occupant vehicles will provide Edmonton with a well-maintained and integrated transportation network. Increased use of these options will maximize overall transportation system efficiency and support the City’s urban planning, livability, financial, economic and environmental sustainability goals.”

And the new elaboration reads:

“Through this goal, the City recognizes that a transportation system that is designed to support a range of travel options will increase the number of people and the amount of goods that can move efficiently around the city, while supporting the City’s goals for livability, urban form, financial, economic and environmental sustainability. Creating this 21st century sustainable and globally competitive city means offering choice. It will allow Edmontonians of all ages and abilities to safely walk, bike, ride transit, ride-share or drive to the places they need to go. The trade-offs needed to achieve this vision will create an integrated transportation system with greater travel choices for Edmontonians.”

The connection to the other goals is still present in the new wording, but not at the expense of highlighting the desire for alternatives to the car. There’s also the suggestion that trade-offs will need to be made in order to create a system that offers choice – we can’t have it all without making some hard decisions. The new goal is much more approachable now that “mode shift” is gone.

New Outcomes

Alongside this change, Council approved 12 new corporate outcomes, replacing the 20 that had previously been approved. Through their discussions, Council felt the outcomes should be specific and measurable, and provide a clarity of purpose. They wanted to simplify the approach. Here are the 12 outcomes they ended up with:

  1. Edmonton is attractive and compact
  2. The City of Edmonton has sustainable and accessible infrastructure
  3. Edmontonians use public transit and active modes of transportation
  4. Goods and services move efficiently
  5. Edmontonians are connected to the city in which they live, work, and play
  6. Edmontonians use facilities and services that promote healthy living
  7. Edmonton is a safe city
  8. The City of Edmonton’s operations are environmentally sustainable
  9. Edmonton is an environmentally sustainable and resilient city
  10. The City of Edmonton has a resilient financial position
  11. Edmonton has a globally competitive and entrepreneurial business climate
  12. Edmonton Region is a catalyst for industry and business growth

Gone are words like “minimized”, “supports”, or “strives”. The new language seems less open to interpretation, which is a good thing for determining progress. The next step is for Administration to prepare measures and targets based on these outcomes and to update The Way Ahead (there are currently 65 approved measures and 27 approved targets).

Results?

It’s great that Council wanted to strengthen the transportation goal and that they have simplified the outcomes. Most of this strategic planning was completed by previous Councils, so the exercise probably helped to ensure our current Councillors feel a sense of ownership. But the challenge remains: we need to implement the plans and see results. An annual report on progress will go to Council next year, based on the new outcomes, measures, and targets.

Edmonton’s Valley Line LRT moves forward with commitment from the Province

It was the announcement Edmonton was hoping for last Thursday when the Province unveiled its Budget 2014: money for southeast LRT extension to Mill Woods.

Valley Line LRT Funding Announcement

Edmonton’s Valley Line LRT is moving forward after the Province today made a commitment to provide up to $600 million to help finance the project. In a prepared statement, Premier Alison Redford said:

“Alberta is preparing to welcome a million new residents over the next decade, many of whom will be choosing communities like Edmonton as their home. Our Building Alberta Plan is helping municipalities build public transit systems to accommodate growth and make it easier for Albertans of all ages and levels of mobility to get where they need to go.”

In stark contrast to his disappointment last Thursday, Mayor Don Iveson was understandably pleased with today’s result, calling it “a momentous occasion”:

//platform.twitter.com/widgets.js

Today’s announcement was a bit over-the-top in my opinion, with Premier Redford, cabinet ministers, and MLAs arriving at Churchill Station via LRT. I think Mayor Iveson picked up on the pomp as well, joking that he hoped the ministers enjoyed their trip on the LRT.

Valley Line LRT Funding Announcement

It was a good opportunity for Edmontonians to show support for LRT expansion however, with students from City Hall School holding up #yeg4lrt signs at the top of the escalator. There was a sizable crowd gathered and lots and lots of media on hand to capture the event. If you’d like to watch the announcement, you can see the raw footage here.

What the Province has committed to is:

  • up to $250 million under GreenTRIP over three years beginning in 2016-17 upon approval under the second call for GreenTRIP projects,
  • up to $150 million in matching provincial funding if the federal government approves this project under the new Building Canada Fund beginning in 2016-17, and
  • up to $200 million in an interest-free loan to be repaid by the city over 10 years, fully backed by the Alberta Capital Finance Authority (ACFA).

As Mayor Iveson noted today, only $400 million of that is new money. The interest-free $200 million loan is simply a creative way to bridge the gap.

Valley Line LRT Funding Announcement

It is unusual though not unprecedented for the Province to offer interest-free loans to municipalities through the Alberta Capital Finance Authority (ACFA). For instance, a program known as “ME first!” launched in September 2003 and provided interest-free loans to encourage municipalities to achieve energy savings in their operations. It is common for the City to receive loans from ACFA for infrastructure projects, with typical interest rates ranging from 1.6% to 3.3%. Some projects that the City has previously borrowed for include the Whitemud Drive/Quesnell Bridge rehabilitation, the Walter Bridge replacement, and the NAIT LRT line. Any loans would be subject to the Municipal Government Act, which outlines debt limits and other restrictions. Edmonton is well within both the provincial debt limit and its own more strict limits.

Technically the money won’t start flowing until 2016, which perhaps not coincidentally happens to be the pre-election budget. It certainly did feel like a politically motivated announcement today. The Province received immense pressure from Edmontonians after last week’s budget and Mayor Iveson and his colleagues on Council did a good job of harnessing that to their advantage (the mayor even played along with the #SadDonIveson meme).

//platform.twitter.com/widgets.js

As Dave noted today:

//platform.twitter.com/widgets.js

Still, the assurance from the Province means that the City can keep the project moving forward, and that’s a win for Edmonton. We won’t lose a construction season, and the federal funding will likely be received without issue. Mayor Iveson confirmed:

“Knowing that we have a clear pathway to apply for those dollars allows City Council to consider moving ahead to the next step of this journey.”

The mayor thanked Council, our regional neighbours, and the ministers at the Province for working hard to get the deal done.

Valley Line LRT Funding Announcement

I know many people have been working on this for a long time, but I think Mayor Iveson deserves a lot of credit for making this happen. He expressed disappointment and frustration last week, but did not alienate the cabinet ministers he needed to work with to move things forward. He kept the lines of communication open, and clearly said the right things.

Today’s news, while positive for the Valley Line LRT, is not the long-term commitment that the mayor has been seeking, but it is another step in the right direction.

Valley Line LRT

Here’s a look at what the Valley Line LRT will look like from Mill Woods to 102 Avenue downtown (subject to change):

The City’s website has already been updated with details related to the funding:

“Thanks in part to timely commitments by our provincial and federal partners, the Valley Line will remain on schedule for a construction start of 2016, aiming to be open to the public by the end of 2020.”

The next step is a Request for Proposals to shortlist qualified consortia (groups of affiliated companies) that bid on the project. That stage is expected to take three months.

Keep up-to-date on the Valley Line LRT here or sign up for email updates.

Province to Edmonton’s City Council: “You’ll like the 2014 budget…just kidding!”

Things were looking up for LRT expansion in Edmonton. As recently as a few weeks ago, Mayor Iveson sounded optimistic that the Province was going to provide money for LRT. Other members of City Council had also received positive indications from the Province. But talk is cheap, and the Province didn’t follow through with today’s budget, as Mayor Iveson made clear:

“Not in a position to celebrate anything today at this point. Little bit of disappointment that yesterday’s message and really the message our Council has been consistent about since last year hasn’t quite gotten through yet.”

The Province unveiled its 2014 Budget this afternoon, saying it “delivers the core services Albertans expect, makes strategic investments in innovation to improve the lives of Albertans today and into the future, and strengthens new and existing infrastructure to address the demands of our growing province and economy.” Unfortunately, LRT was not deemed a priority as evidenced by the complete lack of commitment to funding its ongoing expansion in Edmonton and Calgary.

The original GreenTRIP fund of $2 billion, created by the Stelmach government in 2008, has not been increased. MSI funding increased slightly, but not nearly enough to fund the LRT expansion to Mill Woods. Besides, as Mayor Iveson again pointed out today, Edmonton has a need for LRT funding on top of all the things that MSI funding is used for in other municipalities – building libraries, recreation centres, etc. The lack of increase in GreenTRIP funding was especially disappointing to the mayor:

“My interpretation of long-term commitment to GreenTRIP isn’t just saying we’re going to roll out all the money we announced serveral years ago by 2019 and announce this year’s money like its new when its actually money that we’re putting into the NAIT line today because its money that was announced previously.”

He clarified yet again what a long-term commitment would look like:

“For me, a long-term commitment to transit would be an open-ended or ten year commitment to sustained levels of funding for rapid transit expansion in our province.”

The reaction from local leaders was disappointment, as expected. “There’s no new commitment to transit here,” Mayor Iveson said.

//platform.twitter.com/widgets.js

//platform.twitter.com/widgets.js

//platform.twitter.com/widgets.js

//platform.twitter.com/widgets.js

There are two key risks the City faces by not receiving funding for LRT expansion from the Province. The first risk is that we miss yet another construction season, which could add around $65 million to the total cost of the project. The City has a deadline of April 30 to try to get all of the necessary funding in place. If that date isn’t met, then the completion of the Southeast LRT expansion by 2019 is in jeopardy.

The second risk is that the federal funding Edmonton has applied for under the P3 Canada program could be at risk if construction doesn’t begin by the end of 2015. “There is a timeline on the P3 grant,” Mayor Iveson said. “If we were to lose another year, then we would potentially begin to lose some of the federal funding, and then we’d really lose momentum.”

Mayor Don Iveson

But the biggest issue here is that the Province made noise about a long-term commitment to LRT, and simply hasn’t delivered. Mayor Iveson expressed his frustration with this:

“Frankly I received a lot of mixed messages from the Province over the last six to eight weeks, that we’d be happy, that we should manage our expectations, that we’d be satisfied, that we’re asking for too much, and often from the same people, so that is a frustration.”

Still he tried to remain optimistic, adding, “that just tells me that things are fluid still.”

You can listen to Mayor Iveson’s full remarks here:

If there wasn’t already a trust issue between City Council and the Province, there most certainly is now. Conversations can only be considered productive if they actually lead to an outcome that all sides are happy with. If the Province wasn’t prepared to make a commitment now, they should have made that clear to the mayor and the rest of Council.

Asked what he thought about his first provincial budget experience since taking office, Mayor Iveson sighed audibly. “That’s what I think,” he said. Ever the optimist, he said he remained dedicated to working with the Province to find a positive outcome for the city. “I think they’ve figured out in the last 24 hours that we really mean it, this is really important to us.”

You can read more about the Province’s Budget 2014 here.

Recap: Mayor Iveson’s 2014 State of the City Address

Mayor Don Iveson delivered his first State of the City address today in front of an absolutely packed crowd at the Shaw Conference Centre. Hosted by the Edmonton Chamber of Commerce, the State of the City luncheon attracted more than 2200 people including Councillors, MLAs, MPs, as well as business and community leaders, all eager to hear what our new mayor would say. Would he make a statement like Mayor Mandel did (by declaring “no more crap”) in his first address? Would he dump on the Province like Mayor Mandel did (lamenting the treatment of post secondary education in Edmonton) in his last address? Or would he set a completely different tone?

State of the City 2014

Though Mayor Iveson’s speech today may have lacked a lightning rod comment like the infamous “no more crap”, it had its moments. Looking right at Premier Redford, our mayor called for the Province to come to the table on funding for LRT expansion:

“Madam Premier, never has the opportunity and timing to fully build out Edmonton’s LRT network been more worthy of your government’s leadership, commitment and support. Show that you understand the needs of this city in the same way that my Council does. Show Alberta’s capital city that we are worth investing in.”

It was a powerful moment, and the audience erupted into applause after he delivered the words. Without question that part of the speech is what we’ll be talking about years from now.

Mayor Iveson opened and closed his speech recognizing the important role that indigenous peoples have played in Edmonton’s history, and the important role they’ll play in our future.

“Ladies and gentleman, a new, more confident Edmonton has emerged – building upon our rich heritage, leveraging our advantages, and – most importantly – unafraid to challenge ourselves to do even better.”

He noted that Edmonton will host the Truth and Reconciliation Commission of Canada’s national event later this month. “Without recognizing our shared history and learning from it, we have no hope of making change,” he said.

Though he touched on topics like public engagement, roadway maintenance, and the City Centre Airport, Mayor Iveson focused the bulk of his time on ending poverty, the global competitiveness of the region, LRT expansion, and the big city charter.

State of the City 2014

On poverty, Mayor Iveson looks set to keep an election promise, announcing that next week Council will consider his proposal to elevate the existing Poverty Elimination Committee (of which I have been a proud member) to a task force. “Simply managing poverty is not working,” he told the crowd. He called upon everyone in attendance to think about what they could do to “unleash the next generation of entrepreneurs from unlikely circumstances.” Mayor Iveson also recognized the importance of aligning with the Province’s commitment to eliminating child poverty in Alberta.

“Poverty is complex. Its causes are multi-facted, interlinked and anything but straightforward. Many are afraid to tackle it. But I am not.”

Using language that should by now seem familiar, Mayor Iveson next turned his attention to the Edmonton region. “If we want to continue to outperform other city regions in Canada, then we must work together much more effectively – and there can be no delay,” he said. Amalgamation isn’t on the horizon but he recognized that business leaders are frustrated. “For the region to achieve results, we must work together much more effectively on economic development,” he said. Again, the mayor issued a challenge, calling on his fellow mayors to consider the role they play:

“What will you do differently…how will you think differently…are you ready to look ahead and ensure that our region’s ability to compete globally for our mutual long-term benefit is always at the forefront of our deliberations?”

He briefly discussed annexation, saying that “boundary changes are a natural part of these discussions.” Mayor Iveson said that “Edmonton’s future growth must be balanced with a healthy mix of residential and employment areas.”

State of the City 2014

Though his pointed comments to Premier Reford were the most memorable part of Mayor Iveson’s remarks on LRT, he had much more to say. “To remove all doubt,” he told the audience firmly, “this Council unanimously declared LRT expansion as its priority for new infrastructure investment, beginning with the long-awaited Valley Line from Mill Woods to downtown.”

Most of City Council has been saying optimistic things about the Province providing funding for LRT, and Monday’s throne speech certainly sounded like a step in the right direction. We won’t know for sure until tomorrow if anything has changed however, when the budget is released.

The final major topic that Mayor Iveson addressed was the Big City Charter. “Big cities fuel a large part of the province’s economic dynamism,” he said. Citing work underway with the City of Calgary that has led to a closely aligned vision for such a charter, the mayor expressed his hope that discussions with the Province will be productive.

“We have reached the point where Alberta’s big cities have outgrown the one-size-fits-all Municipal Government Act and our collective efforts are better spent focused on a big city charter. What is needed is a real partnership between Alberta’s big cities and the provincial government.”

Unfortunately, I think Mayor Iveson again missed an opportunity to talk about what a big city charter might look like. I certainly applaud the ongoing effort to negotiate a better deal for big cities, but it would be much easier to ask the hundreds of Edmontonians in the room for support if they could understand and talk about it. The big city charter still seems nebulous.

State of the City 2014

Mayor Iveson spoke today with the same confidence and measured delivery that attracted Edmontonians to him during last fall’s election. Will it go down as his most memorable speech? Likely not. But I think he said the right things, in public, to the right people. Most of the folks in the room were already Iveson supporters, so winning them over wasn’t the goal. Instead, he delivered a clear message about what’s important to Edmonton and offered insight into how we should tackle key issues.

“My responsibility, and my Council colleague’s responsibility, is to steer us, focused on an ascendant Edmonton. Great cities emerge when conditions are ripe for unprecedented cooperation, creativity and disruptive change. The cities that embrace this will thrive while cities that are content with today will lag and whither. I will not stand for that in Edmonton. And, given what we hear from Edmontonians every day, neither will you.”

You can read the full text of Mayor Iveson’s remarks here in PDF. You can read my recap of last year’s State of the City here.

Does high speed rail have a future in Alberta?

Last week I attended a public meeting on high speed rail in Alberta (which I typically abbreviate ABHSR). The issue is being considered by the Standing Committee on Alberta’s Economic Future, an all-party committee consisting of 18 MLAs. As part of the process, the committee has now heard from the public in Calgary, Red Deer, and Edmonton, and is encouraging additional written submissions by March 31. I hope at least a few Albertans take them up on that, because their “public” meeting was poorly publicized and required going past three security checkpoints.

Alberta High Speed Rail Public Meeting

Here’s the stimulus provided by the committee on the idea:

  • It could offer service between Edmonton and Calgary (including a stop in Red Deer) with a trip time of one to two hours at speeds of 200-500 km/h.
  • One-way ticket prices have been estimated at between $66 and $142.
  • Capital costs have been estimated at $2.5 to five billion, but could be significantly higher.
  • A route would be chosen and land would be acquired along the route for tracks and stations.
  • Overpasses or underpasses would likely have to be built to accommodate many of the road crossings or, alternatively, bridges above any roads the track would cross could be constructed.

Clearly the idea is intriguing. A hundred bucks to get to Calgary in less time than it would take to drive? Sign me up! Driving is stressful, I could read or do some work on the train, there are lots of positives, for sure. But is Alberta ready? Is this an investment we’re prepared to make now?

There were some interesting viewpoints put forward at the meeting. Some felt the time is right, and that a project like this could allow us to harness the talents of all the smart, creative, and innovative people we have throughout the province. Others expressed concern that our population isn’t big enough to warrant such a project. And still others argued that automated, driverless cars are coming and will make the entire idea irrelevant (as exciting as the work Google and others are doing in this area is, there are significant hurdles still to overcome, so I’m not holding my breath).

Technically, the project sounds feasible. A few speakers talked about Maglev technology that has been deployed in a number of other places, notably in Asia. One speaker, Deryck Webb, said Maglev combined with vacuum tubes was the way to go (what he described sounded very similar to Elon Musk’s Hyperloop). I think the key issues are financial and political, not technical.

Alberta High Speed Rail Public Meeting

The issue last came up in 2009, when a report was issued assessing the potential for service between Calgary and Edmonton. At the time I wrote:

“I personally think if the province is going to be spending money on transit, it should be on city and regional transit. Both Edmonton and Calgary could use the assistance to improve their respective transit systems…”

I still feel that way today. If we’re going to spend a few billion dollars, let’s spend it on LRT first.

This is the message our local leaders are sending to the Province. One of the written submissions the committee has received thus far was from the Edmonton International Airport. President and CEO Tom Ruth wrote the following:

“Given the lack of local networked options in the Edmonton Region, we agree with the position of the City of Edmonton and the Edmonton Economic Development Corporation (EEDC) that the priority should be to ensure there are fully developed networks in advance of HSR; including Light Rapid Transit (LRT) service fully developed within the Edmonton Region, with connectivity to EIA. Until these intra-regional options are fully built out, the utility of HSR is severely limited.”

Maybe high speed rail is in Alberta’s future, but I hope it’s after we have developed the LRT networks in Calgary and Edmonton.

You can see the full transcript of last week’s public meeting here (or in PDF here). You might also be interested in the Reddit thread on the issue. If you’d like to submit something to the committee, send it to economicfuture.committee@assembly.ab.ca. The deadline is March 31, and all submissions and the identities of their authors will be made public.

Another small step forward for Edmonton’s Southeast LRT extension

Prime Minister Stephen Harper today introduced the new Building Canada Plan, “the largest long-term infrastructure plan in Canadian history, providing stable funding for a 10-year period.” The highlight of the new plan is the $14 billion New Building Canada Fund, a potential source of funding for projects like Edmonton’s planned Southeast LRT extension.

valley line lrt

Known as the Valley Line, the Southeast to West LRT extension would run 27 km from Mill Woods to Lewis Farms. The City hopes to construct the expansion in phases, starting with a $1.8 billion leg from Mill Woods Town Centre to 102 Street downtown. The City has already committed $800 million to the project, and now needs the federal and provincial governments to contribute their share.

Despite some opposition, City Council approved the use of a public-private partnership to build the extension, enabling the City to access funding through P3 Canada. In March last year, P3 Canada awarded $250 million toward the project.

Mayor Don Iveson

Though many details about the new Building Canada Fund are still to come, Mayor Don Iveson held a press conference this afternoon to discuss how it might help the City with the LRT expansion. In the ideal case, the City would receive another $150 million for the project, taking the total federal contribution to $400 million. Mayor Iveson said:

“That shows the federal government is seriously committed to investing in transit, maybe to not the level that mayors across the country would like, but it’s an opening to further discussion about the importance of national investment in transit infrastructure.”

Though he praised the efforts of the federal government, he also shared his thoughts on what he’d like to see in the future:

“Long-term, I would like to see a dedicated federal investment in rapid transit, over and above these baseline Building Canada commitments.”

Here’s the audio from Mayor Iveson’s press conference today:

If the City were to receive the funding it hopes to from Building Canada, that would bring the funding gap down to $365 million (the City has $235 million left over from Stelmach’s fund for green transit that mostly went to the North LRT to NAIT). The Government of Alberta needs to come to the table, and Mayor Iveson sounded optimistic that could happen:

“We’ll keep on talking to ministers and MLAs and we’ve been having a lot of those conversations lately and they’re very receptive. They’re working within their own constraints, and their own competing priorities, but I believe they’re trying to find a way.”

I’m much less optimistic. Both Calgary and Edmonton have made it clear that rapid transit is their top priority, but Premier Alison Redford’s government has consistently avoided making any commitments. Sooner or later, the province is going to have to either come to the table on LRT funding, or as David Staples wrote last month, “we need to elect a government that can make it happen.”

If the funding were secured by the spring, construction on the Southeast LRT could begin as early as 2016 with the extension opening by 2020.