The Metro Line is open: Edmonton’s LRT now extends north to NAIT

Today the oft-delayed Metro Line LRT extension from Churchill Station to NAIT opened. The 3.3 km extension adds a second operational line to Edmonton’s LRT Network Plan, and features the first new stations in four years. But today’s launch was very different than the two most previous extension openings, to South Campus in 2009 and Century Park in 2011. Those extensions opened with great fanfare featuring politicians making speeches and shaking hands. The Metro Line opened quietly this morning with no ceremony.

MacEwan LRT Station
Train to NAIT leaves MacEwan Station

The Metro Line features three new stations: MacEwan, Kingsway/Royal Alex, and NAIT. The extension is expected to add 13,200 weekday riders to the system, and ETS says it has “capacity for considerable growth” once the line eventually extends into St. Albert.

The service that launched today isn’t exactly what was planned, of course. The line has been repeatedly delayed, ostensibly due to issues with the signalling system. The Metro Line was planned to open in April 2014, but here we are in September 2015 with what the City is calling a “staged approach” to bringing it into service. Here’s what that means:

  • Metro Line trains will run every 15 minutes between Century Park and NAIT.
  • They will also occasionally run between Health Sciences/Jubilee and NAIT (weekdays after 10pm, Saturdays after 7pm, and all day Sundays).
  • Every third train running between Churchill and Century Park will be a three-car Metro Line train (most of the time).
  • Trains are operating with “line of sight” which restricts the speed of trains between MacEwan and NAIT to 25 km/h, half the planned speed.
  • This means travel time between Churchill Station and NAIT is approximately 14 minutes.

Sharon and I decided to check out the new extension this afternoon, starting our journey from our home station at Bay/Enterprise Square. It’s been chilly and raining all day (and still is as I write this) but that didn’t stop us!

Bay/Enterprise Square LRT Station

The Metro Line was designed to operate between NAIT and the existing Health Sciences Station, so both the Metro Line and Capital Line share the stations in between (and actually will share stations all the way to Century Park as part of this interim service). That means you need to pay attention to the destination of the train you’re boarding.

Edmonton LRT
On the train!

Though there are clear announcements, this is going to be an issue for new riders. As our train was leaving Churchill Station, another announcement was made and a couple in front of us realized they had gotten on the wrong line. I expect this’ll happen quite a bit over the next few weeks.

It’s just a few moments after the track returns above ground that you arrive at MacEwan Station. I would not be surprised at all if it is renamed MacEwan/Rogers Place at some point in the future. The new arena is such a major part of the station that it almost seems inappropriate that it’s not reflected in the name!

MacEwan LRT Station
MacEwan LRT Station

This station we had previously explored as it’s just a short walk from home. Thinking about it now, it would have been much faster to walk and catch the train there than waiting for a Metro Line train to take us from Bay/Enterprise Square.

MacEwan LRT Station
Future walkway to Rogers Place (and 104 Street) from MacEwan Station

MacEwan Station is just a short walk across 105 Street to MacEwan University. The landscaping and park around the station is quite attractive, though it can be a little confusing at first where to enter and exit the platform (at least from the west side).

MacEwan LRT Station
MacEwan Station

Upon leaving MacEwan Station you immediately notice the reduced speed of the train. It feels comically slow at times. Still, riding the train to NAIT or Kingsway is certainly convenient, even if it takes a few minutes longer than expected.

Kingsway/Royal Alex LRT Station

Aside from being close to the Royal Alexandra Hospital, the Kingsway/Royal Alex station is also adjacent to the relatively new bus terminal. If you’re a transit rider, the new station is going to be great. If you’re a driver though, be prepared to wait.

Kingsway/Royal Alex LRT Station

The longest wait seemed to be for cars turning east onto 111 Avenue from 106 Street. There wasn’t much traffic today, so the waits probably weren’t too bad, but during rush hour I could see a 10 minute or longer wait being very realistic. The rumor flying around this weekend is that waits will last 16 minutes or more, but the City says this won’t be the case. “To be clear — the City does not expect the Metro Line to cause 16 minute traffic delays at these intersections all the time,” they wrote.

Kingsway/Royal Alex LRT Station
Trains pass each other at Kingsway/Royal Alex Station

I really like the design of the station, with its enclosed, heated waiting areas and very attractive wood features. Oddly though, it’s probably faster to walk to Kingsway Mall from NAIT Station than it is from Kingsway/Royal Alex Station. That’s because you have to cross two roads to get to Kingsway Mall, not to mention waiting for trains to go by (which are slower than normal, remember). So this will probably be the station I use least, unless I need to make a bus transfer.

NAIT LRT Station

Once the train very slowly makes its way up 106 Street and across Princess Elizabeth Avenue, you arrive at NAIT Station. This is going to be a big win for students and means that all of our major education institutions are now more or less connected via LRT (with NorQuest getting even better connectivity when the Valley Line LRT opens).

NAIT LRT Station
NAIT Station with Kingsway Mall to the left

As mentioned it’s just a short walk across Princess Elizabeth Avenue to the Sears side of Kingsway Mall. Unfortunately the sidewalk ends almost as soon as you get to the south side of the street, and you’re left dodging vehicles racing in and out of the parkade. That’s one improvement that could definitely be made.

NAIT LRT Station
The current end of the line at NAIT

NAIT Station is currently the end of the line, but if you look northwest you can see what will eventually become Blatchford (which will have its own LRT station).

At NAIT Station
Selfie at NAIT Station!

Even though this “staged approach” is not ideal, it’s very exciting to have the Metro Line open at long last. Our experience today was very positive, but the real test will come Tuesday morning as students are back to school and everyone else is back to work. You can learn more about the Metro Line opening at the Transforming Edmonton blog.

Lincoln Ho of Yegventures rode the very first train this morning – watch his YouTube feed for the video. You can see more photos from our trip today here.

Who or what is to blame for Edmonton’s Metro Line LRT delays?

Why was the Metro Line LRT delayed and when will it become fully operational as designed and intended? We still don’t know the answer to the latter question, but the reasons for the delay have become more clear thanks to the latest report from the City Auditor.

Metro Line LRT
A train! On the Metro Line!

The Auditor’s report found that project management roles and responsibilities were not clearly defined or understood, opening dates targeted were unrealistic, status reports were not written down or communicated effectively, contract management practices were inadequate, and Council was not sufficiently kept informed. Incredibly, “Council did not receive formal updates on project progress until December 2013 when construction was supposed to be complete.” The report makes three recommendations, all of which Administration has accepted.

The Metro Line is a hot topic in Edmonton right now, and Edmontonians are not happy about it. Lots of folks are looking for someone to blame, and for good reason – the project is more than year behind schedule and we still don’t know when it’ll be “done done” as opposed to “done but”. And while I think holding Administration accountable is going to be a critical part of restoring public confidence in the City’s ability to manage large projects, what’s less clear is who that blame should fall upon.

Dorian Wandzura
Dorian Wandzura

Dorian Wandzura started as the GM of Transportation Services on September 3, 2013. He took over from Bob Boutilier, who retired from the role on July 31, 2013. Formerly a deputy GM with the Toronto Transit Commission, Boutilier was credited with getting “80% of Edmonton’s long term Light Rail Transit network has been designed, planned or constructed” during his tenure. He may now also be credited with leaving the Metro Line project in a state of disarray. While Wandzura has made some mistakes along the way, it’s pretty clear now that he inherited a mess. And not just one actually, as he’s also having to deal with the Walterdale Bridge and 102 Avenue Bridge delays, among other projects.

Bob Boutilier
Bob Boutilier

What about Charles Stolte, the former GM of ETS who was fired in June? It’s not clear exactly why Wandzura let him go, but there’s some suggestion it was because of philosophical differences rather than as a result of delays to the Metro Line. He would no doubt have been involved in the signalling work, but it’s unlikely that he was primarily responsible for the debacle.

ETS Execs
Charles Stolte, right

Then there’s Wayne Mandryk, who has been in charge of LRT Design and Construction since 2008. Until the last major city reorganization in June 2011, his branch was part of a separate department known was Capital Construction. Since then it has been part of Transportation Services. The branch “manages contracts for design and construction, identifies and evaluates project delivery strategies, and coordinates construction with other city departments and utilities.” Until the spring, it was most often Mandryk that handled public communications about the Metro Line. Now Wandzura has been handling that himself. But it doesn’t appear that switch has anything to do with confidence in Mandryk as he’s currently filling Stolte’s role as well until a replacement is found.

Wayne Mandryk
Wayne Mandryk

The Auditor’s report seems to place quite a bit of blame on both Boutilier and Mandryk:

“Schedule risks emerged as planning and procurement activities progressed. However, we found no formal documentation from LRT Design and Construction to the Transportation Services General Manager advising him of emerging issues and potential delays. We were advised by LRT Design and Construction that the culture at the time was to provide verbal rather than written reports.”

Mandryk’s department didn’t provide written reports when they should have but Boutilier would have been most responsible for allowing a culture of verbal updates to flourish.

Simon Farbrother
City Manager Simon Farbrother with Councillor Amarjeet Sohi

So up we go, to the top. City Manager Simon Farbrother started at the City of Edmonton in January 2010. That’s after the Concept Plan for the Metro Line was approved, but before the contracts were awarded and long before work began. Certainly he’s going to have to answer some difficult questions from Council next week, and I expect he’ll be ready to make some changes, but it’s hard to find fault with Farbrother in this case. Throughout his first five years with the City, a key initiative of Farbrother’s has been changing the culture. He’s led a transformation that has made the City more open, creative, and aspirational. Additionally, Boutilier had already been in charge of Transportation for three years by the time Farbrother joined, and so far hiring Wandzura seems to have been a smart move.

Still, the comment Councillor Andrew Knack made this week suggests Farbrother could have done more:

“For such a major city project, there should be a desire for those in the highest (positions), especially if they haven’t heard anything, to get a status update. That’s the discouraging part.”

He’s right. It seems perfectly reasonable to expect the folks in charge to ask for updates. Except that Council doesn’t seem to have asked for updates either, at least not in an official, there’s-a-paper-trail capacity. There were about ten agenda items from mid-2011 through until mid 2013 related to the NAIT LRT, and none of them were about project status.

Mayor Iveson wrote on Monday:

“Not only were the city’s senior managers seemingly out of the loop when contractor performance started to slip in 2011, but City Council was left totally in the dark until late 2013 – which made it all the more difficult for us to hold staff accountable and explain to the public what was going on.”

All of this begs the question, what the heck happened between 2011 and 2013? Why were senior managers and Council so out of the loop on the Metro Line LRT?

Well, there was one thing that pretty much consumed Council and CLT’s attention during that same period of time: the downtown arena.

New Edmonton Arena Construction
Rogers Place rises next to MacEwan LRT Station on the Metro Line

Think about it. The arena debate dominated attention across the city throughout 2011 and 2012. It also included a lot of secret, private meetings between Administration, the Katz Group, and City Council, which plenty of people picked up on and criticized, myself included. That could have contributed to the culture of verbal reporting.

Here’s the timeline:

Most other attention-hogging projects were done by the time problems with Metro Line project started. The Quesnell Bridge expansion was completed in September 2011 and the 23 Avenue Interchange opened the following month. The winter of 2012/2013 was a particularly bad one for potholes and that did attract a lot of attention and criticism, but we have potholes every year.

I’m not saying the downtown arena project is to blame for the Metro Line delays. Correlation does not imply causation, of course. And that project is currently on time and budget because of solid project management, and I don’t want to take anything away from that. But the timeline above fits together just a little too well, doesn’t it?

As Paula Simons wrote in her column on the auditor’s report, “there’s no smoking gun in this audit – just smoke and murk.” There are also a lot of assumptions being made in trying to explain the delays – the splitting of the contracts, the inadequate project management practices, Thales missing deadlines. Maybe the simplest answer is the right one: the City and Council were distracted.

My slightly more complicated take? The arena distraction didn’t help but the biggest issue was that the culture of Transportation Services needed to change, which is happening now that Boutilier is gone and Wandzura is in.

We’ll find out more on Monday afternoon as Council discusses the auditor’s report.

Metro Line LRT delayed again until Spring 2015, maybe, hopefully

The City held a press conference late this afternoon to provide an update on the Metro Line LRT extension to NAIT. They should have waited until February 2, because once again we learned that the opening of the new line has been delayed. The new target date is May 2015, more than a full year after the extension was originally slated to open.

2014-12-07 McEwan Station
MacEwan LRT Station in December 2014, photo by Darren Kirby

Today’s news release thanked Edmontonians for their patience and used much more careful language than previous delay announcements:

“Based on the most recent testing schedule provided by Thales Rail Signalling Solutions Inc., the City of Edmonton is cautiously optimistic the Metro Line LRT will open to public service in spring 2015.”

Cautiously optimistic is a long way from confident. The reason for the delay is the same thing we’ve heard since the project was first delayed – the contractor is having problems with the signaling system:

“Thales appreciates the patience of everyone in Edmonton as we work to complete the signaling system for the Metro Line,” says Thales Vice President Mario Peloquin. “We understand how important this essential transportation infrastructure is for the people of Edmonton, and we remain committed to delivering an outstanding product that is safe, efficient and reliable, and that will serve the city for generations to come.”

The signaling system is responsible for controlling train traffic. It tracks train movements and keeps them on schedule. Part of the challenge is that with the Metro Line, the City is changing the signaling system from a traditional fixed block system to a more modern communications-based train control system, or CBTC. It’s this new signaling system that will enable trains on the Metro and Capital lines to share the same tracks.

Even though construction completed on time and $90 million under budget, the Metro Line still isn’t open. The project has been delayed numerous times over the last year or so:

  • In September 2013, everything seemed on track for an April 2014 opening.
  • In December 2013, the opening was delayed a few months until Spring 2014.
  • In the Spring of 2014, the opening was further delayed until the end of the year. That schedule was reaffirmed over the summer.
  • In October 2014, the opening was delayed again, with February 2015 identified as the earliest possible date.
  • Now, in January 2015, the opening has been delayed until May 2015.

Needless to say, there’s very little confidence in the latest target date.

New Edmonton Arena Construction
MacEwan LRT Station next to the new downtown arena, September 2014

It was in October 2014 that Mayor Iveson called the delays “unacceptable” and asked the City Auditor to review how the project had been managed. Since then, the City has held back $20 million from the $55 million contract with Thales, and the auditor has been investigating.

Now the City says that the latest schedule from Thales would have the handover of the signaling system take place by March 23, 2015. If by some miracle Thales is actually able to meet that date, the City would need approximately 6 weeks to evaluate the system and complete staff training.

“We are very concerned with the ongoing delay of the Metro Line and will continue doing everything we can to hold Thales to their new schedule. Our goal remains the same: to open the Metro Line for safe, reliable public service as quickly as possible.”

On the Metro Line LRT site, the City has made available a slide deck and an FAQ, both in PDF.

metro line delayed

The FAQ tries to explain what has happened and attempts to provide some confidence that the City is providing “increased” project oversight to ensure it gets done. After the number of delays this project has experienced, you have to wonder if sticking with Thales is the right approach, but that’s what the City is doing:

“At present, our best option is to continue supporting Thales to deliver the signaling system. Our expectation is that Thales will meet its commitments. The City has strict project oversight to ensure they do so. If they fail to meet a milestone or if testing does not proceed according to schedule, the City will hold Thales to account.”

Let’s hope the sunk cost fallacy isn’t at play here.

The City says they are “tracking milestones on a daily basis” and have increased resources on the project. “We’re working diligently to help Thales deliver the signaling system by March 23, 2015.” The FAQ even says the City has explored the option of using people to manage train movements in an effort to get the new line open more quickly, but they ultimately decided that approach did not meet requirements for cost, safety, reliability, or efficiency.

Curiously, the final question in the FAQ is, “are you feeling badly about the delay, City of Edmonton?” Here’s the answer:

“Everyone involved with the Metro Line project regrets the delay of this exciting transportation project. We ask for your patience and hope you’ll continue to bear with us as we work towards bringing the Metro Line into service in spring 2015.”

So we’ll have to wait until late March before we can be sure the Spring 2015 opening is actually going to happen. In the meantime, we’d better make sure the same problems aren’t going to plague the Valley Line LRT extension.

LRT Construction Downtown: Short-term pain, long-term gain!

I’m excited about the expansion of our LRT network and what it’ll mean for Edmonton. It’s going to take a while until the entire network is completed, but work is already underway. While I would definitely fall into the YIMBY camp on LRT construction, that doesn’t mean there aren’t annoyances along the way. I just keep reminding myself – short-term pain, long-term gain!

The North LRT to NAIT is a 3.3 km extension from Churchill Station to NAIT with a total estimated cost of $755 million. Construction began in 2011 and over the last couple of years there has been a lot of activity along 105 Avenue and 105 Street in particular. The new line runs right through Sharon’s route to work, so she has experienced first-hand the inconveniences caused by the construction. The City has been proactive about meeting with affected stakeholders, and they even have an interactive map online, but that doesn’t completely make up for the ongoing issues.

North LRT to NAIT Construction

Closures might mean a slightly different route for motorists or a few extra minutes of travel time, but the impact on pedestrians is often much larger. Closed sidewalks can mean large detours into unfamiliar and poorly marked territory. When it’s cold out, a few extra minutes in a vehicle isn’t such a big deal but for a pedestrian it can be (and that makes jaywalking an attractive option). You’re also much more likely to find signs for vehicles than you are for pedestrians. Other issues include construction noise and, thanks to our up-and-down weather, treacherous and messy conditions.

North LRT to NAIT Construction

The new extension is slated to open in April 2014. Short-term pain, long-term gain!

The Central Station LRT Rehabilitation is a renewal rather than an extension. It will repair issues with the roof and ensure the station is functional for years to come. The City is also taking the opportunity to make streetscape improvements to Jasper Avenue between 100 and 102 Street. I work in the Empire Building at Jasper Avenue and 101 Street, which is basically ground zero for the project (and there’s also the First & Jasper construction right across the avenue).

Central LRT Station Construction

The construction team has been good at keeping everyone in the area up-to-date, with notices in the mail and electronic updates delivered through our property manager. That doesn’t mean the daily maze is any less annoying, however. I try to go through the back of the building to avoid the mess altogether, but every few days I need to use the front entrance for some reason, and determining how to navigate through the ever-changing array of fences gets old fast. There’s always construction noise to deal with too, though thankfully there have only been a few occasions when it has been disruptive.

Central LRT Station Construction

I know that travelling down 101 Street for vehicles sucks because traffic moves so much slower through the construction, but at worst you’re looking at a few minutes of delay. Compare that to the impact on pedestrians. Walking from the Empire Building to Scotia Place used to take a few seconds, we’re talking probably 30 steps or so. Now because of the fencing and detours, it takes probably ten times that! That’s a significant impact (though a little extra walking never hurt anyone).

The project isn’t expected to be complete until October 2013. Short-term pain, long-term gain!