LRT is about more than speed

If you’re angry about the Metro Line LRT, then you’ll love Tristin Hopper’s article in today’s National Post. He’s a self-described “fervent – almost fanatical – supporter of public transit” and he doesn’t hold back on eviscerating Edmonton’s latest addition to the LRT network:

“In short, it fails on every single possible justification for why cities should build light rail.”

It’s a colorful piece, complete with a comparison to “a candy company releasing a new chocolate bar called Herpes Al-Qaeda.” But while it’s clear the City of Edmonton made some mistakes and that it would indeed be bad to see them repeated elsewhere, Hopper’s arguments are clearly coming from a place of frustration rather than fact, and he comes off sounding more like a supporter of car culture than the transit booster he claims to be.

Before I get into that, let me say that I’m just as frustrated and disappointed as many of you are with how the Metro Line LRT was handled and how it is still not fully operational as promised. I’ve written a lot about it over the last year, and I’m sure there will be much more to come in the year ahead. There’s no question that the City of Edmonton screwed up on the Metro Line LRT, but Council didn’t do itself any favors by ignoring the project until it was too late either. People have been fired, lessons have been learned, and there’s undoubtedly more fallout to come.

But, let’s not make a mountain out of a molehill, mmkay?

Kingsway/Royal Alex LRT Station

Hopper is right to point out how unacceptable it is that the line breaks down so regularly. And he’s right that due to the signalling system issues, the trains aren’t running as fast as planned. But his article also makes some pretty specious arguments about emissions1 and the impact on ambulances2. Hopper has some nerve adding up the amount of time wasted by drivers waiting for the Metro Line LRT trains to go by, as if those drivers had never before run into rush hour and gridlock. How much “human existence” has commuting by car, a much more dangerous, stressful, and expensive mode of transporation, extinguished? Easier to pick on LRT, I guess.

“The chief problem is that the train was built at grade and cleaves through several major intersections,” Hopper writes. This leads to delays for passengers and a “traffic apocalypse” for everyone else. “I’ve personally clocked a six-minute wait,” he complains. I get it, I hate being made to wait as much as anyone (thank goodness Sharon is a much more patient person than I am). But this is just as silly to highlight now as it was four months ago when the Metro Line LRT opened.

The only reason this extra-six-minutes argument has any appeal at all is that there’s something to blame. Probably every driver has spent far longer than six minutes stuck in traffic on many occasions, but without a train to complain about, those delays are just chalked up to the realities of driving. Over time drivers become oblivious to them. Sure people complain about traffic from time-to-time, but no one is crucifying the City over it like they are with the Metro Line LRT.

Also wrong is complaining about how slow the train ride itself is, especially given that the Metro Line LRT isn’t operating at full-speed yet. Even if it were, LRT isn’t supposed to be faster than other modes of transportation. It can be, in some cases, but it doesn’t have to be and that isn’t the reason to build it in the first place. LRT is primarily about capacity, not speed. And transit is about the network, not a single line.

It’s not the speed that matters

We need not look any further than the existing Capital Line LRT to see that speed isn’t why it has been successful. What if I wanted to get from my house on 104 Street downtown to Southgate Centre? Here’s a look at the trip by mode at three different times for today, according to the fastest option suggested by Google Maps:

7:00 AM 12:00 PM 5:00 PM
Cycling 30-34 minutes 30-34 minutes 30-34 minutes
Vehicle 16-20 minutes 16-22 minutes 16-40 minutes
Bus 38 minutes 38 minutes 41 minutes
LRT 24 minutes 24 minutes 24 minutes

And here’s the reverse trip, going back downtown from Southgate:

7:00 AM 12:00 PM 5:00 PM
Cycling 29-33 minutes 29-33 minutes 29-33 minutes
Vehicle 14-20 minutes 14-20 minutes 14-24 minutes
Bus 37 minutes 37 minutes 37 minutes
LRT 21 minutes 21 minutes 21 minutes

Depending on the time of day, direction of travel, your speed, and lots of other conditions that you have no control over (traffic, weather, etc.), driving is actually the fastest mode of transportation. LRT is pretty quick, but more importantly is consistent and predictable. My travel time in the real world is far more likely to match the prediction for LRT than it is for a vehicle. Not to mention taking the LRT means you can do something productive or enjoyable while you ride, and you don’t have to pay for parking.

That particular example, downtown to Southgate, makes the time to take the bus seem quite unappealing. Again, that’s to be expected given ETS’ approach of having buses feed into the LRT network, something that will also happen with the Metro Line LRT once it is fully operational. If we look instead at an example where there isn’t LRT, we see that the bus can actually be competitive and maybe even faster than travelling by vehicle. Here’s my place to West Edmonton Mall:

7:00 AM 12:00 PM 5:00 PM
Cycling 37 minutes 37 minutes 37 minutes
Vehicle 18-24 minutes 18-26 minutes 20-45 minutes
Bus 29 minutes 27 minutes 33 minutes

And here’s the reverse trip, going from WEM to downtown:

7:00 AM 12:00 PM 5:00 PM
Cycling 36 minutes 36 minutes 36 minutes
Vehicle 18-26 minutes 20-28 minutes 20-35 minutes
Bus 29 minutes 25 minutes 29 minutes

In this example there’s an express bus that travels between WEM and downtown. Again travelling by vehicle could be faster, but it depends greatly on time of day, direction, and unforeseen circumstances like accidents and weather conditions. The bus would also be subject to some of these considerations, so it’s not as reliable as LRT, but it is still a much more viable option in this example. And you can see how an express bus could potentially be a better way than LRT to achieve a fast trip, especially if it were afforded some of the right-of-way and separation advantages of the LRT (the express bus to WEM shares the road with vehicles and follows all existing signals).

This is all just to show that speed isn’t the driving factor behind LRT. If it were, we’d look at those times above and be complaining that it wasn’t always the fastest option. The negative impacts of LRT on traffic are easy to see, at some point vehicles have to wait for trains. But there are positive impacts of LRT on traffic too. More people riding the train means fewer people driving which means (in theory) less traffic than there would otherwise be. That speeds up commute times for everyone.

But the real reason you build LRT is for the capacity. Here’s what the City of Edmonton’s LRT for Everyone PDF highlights:

rails vs roads

One four-car train can move as many people as 600 typical cars. And let’s be honest, you could probably cram even more people onto those trains if you really wanted to. That potential capacity has a real, positive impact on the transportation network as a whole. It makes getting around the city better for everyone.

There are other reasons to build LRT of course. Accessibility, convenience, transit-oriented development, more efficient use of infrastructure, reduced energy use and environmental impact, and much more. But enabling more people to travel more efficiently throughout the city is the big benefit of LRT.

And when you consider it as part of the overall network, with a mix of bicycles, vehicles, buses, and trains, the capacity benefits of buses and trains make an even bigger difference. That’s why shifting Edmonton’s transportation mix to rely less on vehicles is such an important part of The Way We Move.

Set the right expectations

Hopper seems to suggest that fast LRT that doesn’t impact traffic is the only kind of LRT to pursue and that “don’t let idiots build your transit” is the only lesson to be learned from the Metro Line LRT project. But both of these things are off the mark. You don’t build LRT for speed and you can’t avoid idiots, they’re everywhere.

So yes policymakers of Canada, come to Edmonton and learn from the Metro Line LRT. There are clearly things you can do better and a real-world example to examine is better than a theoretical one. But don’t follow Hopper’s lead in setting the wrong expectations for the “decent, right-thinking people” in your cities. LRT is about much more than speed.


  1. For instance, he says the Metro Line LRT “is almost certainly increasing Edmonton’s net amount of carbon emissions.” I guess we’ll have to take his word for it, as he doesn’t provide any evidence to back the claim up. 

  2. Noting that the Metro Line is next to the Royal Alexandra Hospital, he suggests that “any Edmontonian unlucky enough to have a heart attack in one of the northwestern quadrants of the city must wait as paramedics wend a circuitous route through downtown.” This smacks of fearmongering to me, and we’ve already been-there-done-that-tyvm with medevac and the closing of the City Centre Airport. Although he expressed concern with the delays associated with the partial Metro Line operation, AHS’ chief paramedic said that dealing with traffic is not a new problem for paramedics. “We run into these situations all the time,” he told CBC. And as Transportation GM Dorian Wandzura noted in that same article, presumably AHS had already made some operational adjustments, given that the plan was approved and the route defined way back in 2008. 

The Metro Line is open: Edmonton’s LRT now extends north to NAIT

Today the oft-delayed Metro Line LRT extension from Churchill Station to NAIT opened. The 3.3 km extension adds a second operational line to Edmonton’s LRT Network Plan, and features the first new stations in four years. But today’s launch was very different than the two most previous extension openings, to South Campus in 2009 and Century Park in 2011. Those extensions opened with great fanfare featuring politicians making speeches and shaking hands. The Metro Line opened quietly this morning with no ceremony.

MacEwan LRT Station
Train to NAIT leaves MacEwan Station

The Metro Line features three new stations: MacEwan, Kingsway/Royal Alex, and NAIT. The extension is expected to add 13,200 weekday riders to the system, and ETS says it has “capacity for considerable growth” once the line eventually extends into St. Albert.

The service that launched today isn’t exactly what was planned, of course. The line has been repeatedly delayed, ostensibly due to issues with the signalling system. The Metro Line was planned to open in April 2014, but here we are in September 2015 with what the City is calling a “staged approach” to bringing it into service. Here’s what that means:

  • Metro Line trains will run every 15 minutes between Century Park and NAIT.
  • They will also occasionally run between Health Sciences/Jubilee and NAIT (weekdays after 10pm, Saturdays after 7pm, and all day Sundays).
  • Every third train running between Churchill and Century Park will be a three-car Metro Line train (most of the time).
  • Trains are operating with “line of sight” which restricts the speed of trains between MacEwan and NAIT to 25 km/h, half the planned speed.
  • This means travel time between Churchill Station and NAIT is approximately 14 minutes.

Sharon and I decided to check out the new extension this afternoon, starting our journey from our home station at Bay/Enterprise Square. It’s been chilly and raining all day (and still is as I write this) but that didn’t stop us!

Bay/Enterprise Square LRT Station

The Metro Line was designed to operate between NAIT and the existing Health Sciences Station, so both the Metro Line and Capital Line share the stations in between (and actually will share stations all the way to Century Park as part of this interim service). That means you need to pay attention to the destination of the train you’re boarding.

Edmonton LRT
On the train!

Though there are clear announcements, this is going to be an issue for new riders. As our train was leaving Churchill Station, another announcement was made and a couple in front of us realized they had gotten on the wrong line. I expect this’ll happen quite a bit over the next few weeks.

It’s just a few moments after the track returns above ground that you arrive at MacEwan Station. I would not be surprised at all if it is renamed MacEwan/Rogers Place at some point in the future. The new arena is such a major part of the station that it almost seems inappropriate that it’s not reflected in the name!

MacEwan LRT Station
MacEwan LRT Station

This station we had previously explored as it’s just a short walk from home. Thinking about it now, it would have been much faster to walk and catch the train there than waiting for a Metro Line train to take us from Bay/Enterprise Square.

MacEwan LRT Station
Future walkway to Rogers Place (and 104 Street) from MacEwan Station

MacEwan Station is just a short walk across 105 Street to MacEwan University. The landscaping and park around the station is quite attractive, though it can be a little confusing at first where to enter and exit the platform (at least from the west side).

MacEwan LRT Station
MacEwan Station

Upon leaving MacEwan Station you immediately notice the reduced speed of the train. It feels comically slow at times. Still, riding the train to NAIT or Kingsway is certainly convenient, even if it takes a few minutes longer than expected.

Kingsway/Royal Alex LRT Station

Aside from being close to the Royal Alexandra Hospital, the Kingsway/Royal Alex station is also adjacent to the relatively new bus terminal. If you’re a transit rider, the new station is going to be great. If you’re a driver though, be prepared to wait.

Kingsway/Royal Alex LRT Station

The longest wait seemed to be for cars turning east onto 111 Avenue from 106 Street. There wasn’t much traffic today, so the waits probably weren’t too bad, but during rush hour I could see a 10 minute or longer wait being very realistic. The rumor flying around this weekend is that waits will last 16 minutes or more, but the City says this won’t be the case. “To be clear — the City does not expect the Metro Line to cause 16 minute traffic delays at these intersections all the time,” they wrote.

Kingsway/Royal Alex LRT Station
Trains pass each other at Kingsway/Royal Alex Station

I really like the design of the station, with its enclosed, heated waiting areas and very attractive wood features. Oddly though, it’s probably faster to walk to Kingsway Mall from NAIT Station than it is from Kingsway/Royal Alex Station. That’s because you have to cross two roads to get to Kingsway Mall, not to mention waiting for trains to go by (which are slower than normal, remember). So this will probably be the station I use least, unless I need to make a bus transfer.

NAIT LRT Station

Once the train very slowly makes its way up 106 Street and across Princess Elizabeth Avenue, you arrive at NAIT Station. This is going to be a big win for students and means that all of our major education institutions are now more or less connected via LRT (with NorQuest getting even better connectivity when the Valley Line LRT opens).

NAIT LRT Station
NAIT Station with Kingsway Mall to the left

As mentioned it’s just a short walk across Princess Elizabeth Avenue to the Sears side of Kingsway Mall. Unfortunately the sidewalk ends almost as soon as you get to the south side of the street, and you’re left dodging vehicles racing in and out of the parkade. That’s one improvement that could definitely be made.

NAIT LRT Station
The current end of the line at NAIT

NAIT Station is currently the end of the line, but if you look northwest you can see what will eventually become Blatchford (which will have its own LRT station).

At NAIT Station
Selfie at NAIT Station!

Even though this “staged approach” is not ideal, it’s very exciting to have the Metro Line open at long last. Our experience today was very positive, but the real test will come Tuesday morning as students are back to school and everyone else is back to work. You can learn more about the Metro Line opening at the Transforming Edmonton blog.

Lincoln Ho of Yegventures rode the very first train this morning – watch his YouTube feed for the video. You can see more photos from our trip today here.

Who or what is to blame for Edmonton’s Metro Line LRT delays?

Why was the Metro Line LRT delayed and when will it become fully operational as designed and intended? We still don’t know the answer to the latter question, but the reasons for the delay have become more clear thanks to the latest report from the City Auditor.

Metro Line LRT
A train! On the Metro Line!

The Auditor’s report found that project management roles and responsibilities were not clearly defined or understood, opening dates targeted were unrealistic, status reports were not written down or communicated effectively, contract management practices were inadequate, and Council was not sufficiently kept informed. Incredibly, “Council did not receive formal updates on project progress until December 2013 when construction was supposed to be complete.” The report makes three recommendations, all of which Administration has accepted.

The Metro Line is a hot topic in Edmonton right now, and Edmontonians are not happy about it. Lots of folks are looking for someone to blame, and for good reason – the project is more than year behind schedule and we still don’t know when it’ll be “done done” as opposed to “done but”. And while I think holding Administration accountable is going to be a critical part of restoring public confidence in the City’s ability to manage large projects, what’s less clear is who that blame should fall upon.

Dorian Wandzura
Dorian Wandzura

Dorian Wandzura started as the GM of Transportation Services on September 3, 2013. He took over from Bob Boutilier, who retired from the role on July 31, 2013. Formerly a deputy GM with the Toronto Transit Commission, Boutilier was credited with getting “80% of Edmonton’s long term Light Rail Transit network has been designed, planned or constructed” during his tenure. He may now also be credited with leaving the Metro Line project in a state of disarray. While Wandzura has made some mistakes along the way, it’s pretty clear now that he inherited a mess. And not just one actually, as he’s also having to deal with the Walterdale Bridge and 102 Avenue Bridge delays, among other projects.

Bob Boutilier
Bob Boutilier

What about Charles Stolte, the former GM of ETS who was fired in June? It’s not clear exactly why Wandzura let him go, but there’s some suggestion it was because of philosophical differences rather than as a result of delays to the Metro Line. He would no doubt have been involved in the signalling work, but it’s unlikely that he was primarily responsible for the debacle.

ETS Execs
Charles Stolte, right

Then there’s Wayne Mandryk, who has been in charge of LRT Design and Construction since 2008. Until the last major city reorganization in June 2011, his branch was part of a separate department known was Capital Construction. Since then it has been part of Transportation Services. The branch “manages contracts for design and construction, identifies and evaluates project delivery strategies, and coordinates construction with other city departments and utilities.” Until the spring, it was most often Mandryk that handled public communications about the Metro Line. Now Wandzura has been handling that himself. But it doesn’t appear that switch has anything to do with confidence in Mandryk as he’s currently filling Stolte’s role as well until a replacement is found.

Wayne Mandryk
Wayne Mandryk

The Auditor’s report seems to place quite a bit of blame on both Boutilier and Mandryk:

“Schedule risks emerged as planning and procurement activities progressed. However, we found no formal documentation from LRT Design and Construction to the Transportation Services General Manager advising him of emerging issues and potential delays. We were advised by LRT Design and Construction that the culture at the time was to provide verbal rather than written reports.”

Mandryk’s department didn’t provide written reports when they should have but Boutilier would have been most responsible for allowing a culture of verbal updates to flourish.

Simon Farbrother
City Manager Simon Farbrother with Councillor Amarjeet Sohi

So up we go, to the top. City Manager Simon Farbrother started at the City of Edmonton in January 2010. That’s after the Concept Plan for the Metro Line was approved, but before the contracts were awarded and long before work began. Certainly he’s going to have to answer some difficult questions from Council next week, and I expect he’ll be ready to make some changes, but it’s hard to find fault with Farbrother in this case. Throughout his first five years with the City, a key initiative of Farbrother’s has been changing the culture. He’s led a transformation that has made the City more open, creative, and aspirational. Additionally, Boutilier had already been in charge of Transportation for three years by the time Farbrother joined, and so far hiring Wandzura seems to have been a smart move.

Still, the comment Councillor Andrew Knack made this week suggests Farbrother could have done more:

“For such a major city project, there should be a desire for those in the highest (positions), especially if they haven’t heard anything, to get a status update. That’s the discouraging part.”

He’s right. It seems perfectly reasonable to expect the folks in charge to ask for updates. Except that Council doesn’t seem to have asked for updates either, at least not in an official, there’s-a-paper-trail capacity. There were about ten agenda items from mid-2011 through until mid 2013 related to the NAIT LRT, and none of them were about project status.

Mayor Iveson wrote on Monday:

“Not only were the city’s senior managers seemingly out of the loop when contractor performance started to slip in 2011, but City Council was left totally in the dark until late 2013 – which made it all the more difficult for us to hold staff accountable and explain to the public what was going on.”

All of this begs the question, what the heck happened between 2011 and 2013? Why were senior managers and Council so out of the loop on the Metro Line LRT?

Well, there was one thing that pretty much consumed Council and CLT’s attention during that same period of time: the downtown arena.

New Edmonton Arena Construction
Rogers Place rises next to MacEwan LRT Station on the Metro Line

Think about it. The arena debate dominated attention across the city throughout 2011 and 2012. It also included a lot of secret, private meetings between Administration, the Katz Group, and City Council, which plenty of people picked up on and criticized, myself included. That could have contributed to the culture of verbal reporting.

Here’s the timeline:

Most other attention-hogging projects were done by the time problems with Metro Line project started. The Quesnell Bridge expansion was completed in September 2011 and the 23 Avenue Interchange opened the following month. The winter of 2012/2013 was a particularly bad one for potholes and that did attract a lot of attention and criticism, but we have potholes every year.

I’m not saying the downtown arena project is to blame for the Metro Line delays. Correlation does not imply causation, of course. And that project is currently on time and budget because of solid project management, and I don’t want to take anything away from that. But the timeline above fits together just a little too well, doesn’t it?

As Paula Simons wrote in her column on the auditor’s report, “there’s no smoking gun in this audit – just smoke and murk.” There are also a lot of assumptions being made in trying to explain the delays – the splitting of the contracts, the inadequate project management practices, Thales missing deadlines. Maybe the simplest answer is the right one: the City and Council were distracted.

My slightly more complicated take? The arena distraction didn’t help but the biggest issue was that the culture of Transportation Services needed to change, which is happening now that Boutilier is gone and Wandzura is in.

We’ll find out more on Monday afternoon as Council discusses the auditor’s report.

Coming up at City Council: August 17-21, 2015

The Fringe is underway and Council is back to work on Monday which means summer in Edmonton is winding down. Next week we’ll hopefully learn more about the Metro Line LRT, now slated to open with modified service in time for the start of the school year. Council will also be discussing some other contentious topics like Park & Ride at Century Park and the Traffic Shortcutting trials currently underway in Prince Charles and Pleasantview.

Below are links to the meeting agendas for the week as well as some highlighted items and notes.

Meetings this week

You can always see the latest City Council meetings on ShareEdmonton.

Metro Line LRT

Council is slated to receive an update on the Metro Line LRT project on Monday afternoon (it’s a verbal update on the agenda, so no report to look at). It follows news today that the Metro Line LRT will open to public service on September 6:

“Testing a modified approach to Metro Line operations has already begun and ETS training starts Monday,” said Transportation Services General Manager Dorian Wandzura. “We are confident the Metro Line will be carrying passengers for the start of the 2015 school year.”

The line will open with modified service: “line of sight” operation, a 25 km/h speed restriction, headways of 15 minutes between Churchill Station and NAIT Station, and a decrease in capacity along the existing Capital Line. Instead of getting from Churchill Station to NAIT in 7 minutes, it’ll take 14 minutes.

Dorian Wandzura
Transportation Services General Manager Dorian Wandzura

Shortly after the news conference this afternoon, Mayor Iveson cautioned that interim service is “no cause for celebration”:

//platform.twitter.com/widgets.js

This news should make Monday’s meeting more productive, in that Council can focus on what went wrong and how to get the line to full operation rather than spending a bunch of time expressing disappointment that the line still won’t be open. At least I hope that’s the case.

On July 31, the City announced that it had initiated an independent safety audit of the Metro Line signalling system. The audit, to be conducted by Rail Safety Consulting, is supposed to provide confidence in the safety of the system as well as certification in order to open the line. The City is still blaming Thales, saying that “Thales has failed to provide some essential documentation required for the City to accept Thales’ safety certification.”

There has been a lot of concern about the quality of the infrastructure and workmanship of the Metro Line LRT, but the City has said issues are just part of doing business and are dealt with during the warranty period. A separate report on warranty periods for transportation contributed assets says “a warranty period of two years is applied to both City and developer-constructed transportation infrastructure to ensure the construction material utilized and the associated workmanship are performing in accordance with City standards and expectations.”

On a somewhat related note, the City is currently running a survey on “how to make Edmonton’s transit system greater in the future.” You can fill it out online, or look for the street team at events around the city (like the Fringe).

Recreation Centre Security

This report comes to us in response to an inquiry made by Councillor Nickel back in April. He wanted to know more about crime in relation to our large recreation centres. Here’s what the report says:

  • “In general, calls for service to major Community Recreation Centre facilities have been relatively stable year-to-year since 2011, with predictable increases corresponding to the opening of new facilities.”
  • The situation is a bit worse this year, however. “Calls for police response to recreation facilities have more than doubled in 2015.”
  • Why? “The increase in calls for service for 2015 is driven almost entirely by calls to Clareview Recreation Centre.”
  • City staff have also reported an increase in security incidents this year, but say that “these increases can be attributed to the opening of Clareview and the Meadows Recreation Centres and the increased attendance.”
  • The report says that we’ve seen this before, with the Terwillegar Community Crecreation Centre in 2011: “there was a similar surge of incidents, followed by declining incident rates in 2013 and 2014, as facility staff implemented changes to improve facility security.”
  • Which begs the question – are the security incidents taking place at the new centres all different than the ones we saw at Terwillegar?
  • So what’s being done about this? As you might expect, “a strategic planning exercise is currently underway to improve facility security and public safety.”
  • An external security audit for the Clareview Community Recreation Centre has also been initiated.

It doesn’t seem like there’s cause for concern here, just growing pains associated with running such large facilities.

Options & Incentives for Preserving Trees on Private Residential Properties

Mature trees are critical for environmental quality and biodiversity and, as the City says, they “contribute to the livability of our neighbourhoods.” But sometimes they need to be removed, such as “when they conflict with the location of utilities or are unhealthy (diseased/dying).” The question is, can we do anything to preserve them?

“There is no requirement to plant trees or shrubs for low density residential development, thus there is no incentive to retain existing vegetation on site,” the report says.

Mature Residential Trees
Mature Residential Trees, photo by City of Edmonton

There are three options put forward by the City to try to address this:

  1. Create a Minimum Planting Requirement for All Low Density Residential Zones
  2. Develop Planting Ratios and Require Mandatory Landscape Plans
  3. Include Tree Protection in the Zoning Bylaw

Those three are roughly in order of complexity and impact. Option 2 would go beyond the minimum requirements outlined in Option 1, while Option 3 offers the greatest certainty about existing mature trees. The removal of any tree over a certain size would require a development permit, under Option 3.

The City recommends Option 1, “as these changes can be implemented quickly and are supported by stakeholders.” The suggestion is to have landscaping requirements similar to the RF4 and RPL zones, which is one tree and two shrubs per dwelling. “This would allow development officers to encourage the retention of existing vegetation as a way to meet the minimum landscaping requirements.” It would not prevent the removal of existing trees, however.

Century Park Site Park & Ride Options

The current lease agreement between the City and Procura Development (which owns the Century Park Park & Ride site) expires in 2020, so the City needs to decide if its wants to build its own park & ride facility or extend the lease on the existing Century Park site. The original lease with Procura was for five years from 2010 to 2015, with an option for an additional five, one-year renewal terms. The proposed park & ride facility would be located at Ellerslie Road and 127 Street and would be operational by the fall of 2019. It is known as the Heritage Valley Park & Ride.

  • The current site has 1,300 parking stalls, 1,000 of which are leased from Procura.
  • One third of the funding needed for the Heritage Valley Park & Ride was approved in the 2015-2018 Capital Budget.
  • Discussions are underway with the Province to secure land for the site that may fall within the Transportation Utility Corridor.
  • City Policy C554 on Park and Ride states such facilities should be “located primarily at sites where more intensive development is not possible or feasible such as the Transportation Utility Corridor or other major utility rights of way or where such development is not expected to occur in the immediate future.” Since we want to make Century Park a TOD site, having a park and ride site there is inconsistent with this policy.
  • Procura is apparently not interested in extending the current lease, but has been open to discussing various options with the City.
  • The Century Park lot “gets 98% full on weekday mornings” with approximately 1,500 people parking there between 6am and 9am to get on the LRT. It gets to 85% capacity by 7am! Those passengers make up 29% of the total passengers who board the LRT during the morning peak period.
  • Looking at all eight park & ride locations in Edmonton, “the average utilization of park and ride sites on a typical weekday is 97% at LRT stations and 60-70% at Transit Centres.”
  • The proposed Heritage Valley Park & Ride would require a shuttle bus service, which would cost $2.1 million annually after five articulated buses are purchased for $4 million.
  • The City also anticipates an increase in bus usage if the Century Park Park & Ride were to go away, which would require another $1 million annually plus the purchase of ten new 40-foot buses for $6 million.
  • The City does own some land at Century Park where a parking structure could be built but an assessment found that “the high cost of construction would require unreasonably high parking fees or significant subsidies from the City in order to recover the high capital and operating cost.”
  • A position paper developed by the City found that “over 50% of park and ride users come from within 8 km of a site” and are “only willing to back track up to 3 km to a park and ride facility.”

Century Park Station & Park and Ride
Century Park, photo by City of Edmonton

The report does not make a recommendation on what to do. Moving the park & ride from Century Park to Heritage Valley is aligned with the City’s existing policies and future direction, but the question is how to pay for it. The remaining funding required for the Heritage Valley Park & Ride is assumed to come from other sources, but the City says Green TRIP is not an option.

Other interesting items

  • The Edmonton Heritage Council’s 2014 Annual Report is available and talks about the City Museum project. The Heritage Council has focused on “building an audience” rather than acquiring a building thus far, but “anticipates a full business case going forward in 2018 in consideration of the 2019-2022 City of Edmonton capital cycle.”
  • The City recommends that $1.8 million be approved to fund the Fort Edmonton Park Catering Kitchen Project.
  • Utility work on Phase 1 of the new Louise McKinney Riverfront Park project is expected to begin this summer, with construction completed by the end of 2016. Phase 1 includes a new accessible pathway and staircase, while phase 2 consists of a full service restaurant and upgrades to existing facilities, coinciding with completion of the Valley Line LRT.
  • The next priority of Edmonton’s Infill Roadmap is “to conduct the review of the Mature Neighbourhood Overlay.” The City also anticipates updating Residential Infill Guidelines when the new MDP is updated in 2018.
  • The City is recommending that Edmonton’s Energy Transition Strategy and Policy, which I wrote about back in March, be approved, that an Energy Transition Advisory Committee be established, and that the Mayor write a letter to the Province to “explore issues through an enhanced Provincial/City working relationship.”
  • PCL Construction Management Inc. is the construction manager for Rogers Place, and the City is recommending that Council approve consolidating previously approved adjacent construction projects under the same agreement to “provide efficiencies” and “coordination and scheduling of the work.”
  • There’s a report on the Feasibility of Re-Establishing a Natural Channel between Mill Creek and the North Saskatchewan River. Basically in order to build freeways in the 1960s we destroyed many streams and creeks resulting in “water pollution, flooding, erosion, and loss of ecological services.” Now we are looking to mitigate these impacts through a practice called “daylighting”.
  • The overall reliability of escalators in LRT stations in 2014 was 85%. ETS has set a goal of 90% by 2016, with at least 87.5% to be achieved for 2015. As of June 30, 2015, the City says overall year-to-date escalator reliability in LRT stations was 89.3%.
  • An update on traffic shortcutting issues, and in particular the trials underway in Prince Charles and Pleasantview, says that a City Policy for Community Traffic Management will be considered in June 2016. The City says that “the short turnaround time anticipated with this new Traffic Shortcutting pilot project will constrain typical public engagement strategies in favour of faster implementation of traffic management measures to better respond to concerns voiced by the communities.” The next report on the trials is expected to go to Transportation Committee on October 7.

Wrap-up

You can keep track of City Council on Twitter using the #yegcc hashtag, and you can listen to or watch any Council meeting live online. You can read my previous coverage of the 2013-2017 City Council here.

Frustration abounds and public support for future LRT projects in Edmonton is at risk

It has been made abundantly clear that LRT is a key priority for this Council. They reiterated that point again during Tuesday’s update on the delayed Metro Line LRT (the extension to NAIT) and they made it clear to Administration that they’re not happy about the delays, nor about being kept in the dark on progress. “This has been an embarrassment,” Councillor Esslinger complained. “It’s embarrassing to say the least,” added Councillor Sohi. Earlier this week, Councillor Nickel called it “a boondoggle” and Councillor Oshry described the project as “a s**t-show”.

Metro Line LRT

The Metro Line was supposed to open most recently on Sunday, July 5. That follows failed attempts to open on June 7, and May 31, both of which follow countless previous delays. “We are still not in a position to announce an opening date,” Transportation GM Dorian Wandzura told Council when pressed yesterday. The reason? According to the City, there are still issues with the signalling system and Thales is to blame.

Thales claims they’re not the hold up and feel that trains could be operating along the line. They’re still here working on the line, but say that further work consists only of “additional functionality that was not needed for initial revenue service.” We still don’t know why the City and Thales appear to be on such different wavelengths, but there’s speculation that this is all just posturing for a coming legal battle between the two.

As if that wasn’t bad enough, on Monday the Journal revealed that it had acquired a leaked report from 2013 that outlined a number of construction issues plaguing the Metro Line. The report prompted speculation that perhaps there was more to the delayed opening than the signalling system issues the City has consistently cited. Council hammered away at this report during Tuesday’s meeting, and it was clear they were caught off-guard and had not been kept apprised of the situation in previous private updates.

It turns out the leaked report is just one of 80 total reports commissioned by the City on the project. Of the dozen issues identified in that report, nine have been closed and four are live issues that are still outstanding. There’s no word on how many deficiencies were reported and are outstanding from the other 79 reports.

“There are always deficiencies,” Wandzura said. “It’s a normal process that some of those issues are not resolved on opening day, they are dealt with in the warranty period.” Trying to provide context, City Manager Simon Farbrother explained that “every single construction project going on in this city has deficiencies, and that’s normal.” Wandzura added, “if you had a construction project with zero deficiencies, I’d be very concerned.” He reiterated a couple of times that the issues identified in the leaked report “have been or are in the process of being resolved” and that they did not contribute to the delay in opening the line. The City still feels that Thales is to blame for that.

Despite all of this bad news, Brad Smid, project manager for the line, told the Journal that he thought “the project has gone very well.” Yes, he really said that.

Is the City really being made whole?

I get the point that there are always deficiencies. In my world, if you shipped a software product and didn’t find any bugs, that’d be a clear sign that your testing processes are broken. There are always bugs. Still, attempting to reassure Council and the public by explaining that every one of our multi-million dollar projects has problems may not have been the best strategy. It’s clear that not all deficiencies are created equal, but the ones identified in leaked report were discussed as if they were all critical.

“Our objective is to get what we pay for,” said Wandzura during Tuesday’s meeting, adding that the City takes actions “to make the City whole” when deficiencies are found. This could be accomplished by some sort of remediation, financial compensation, or in the worst case, litigation.

Councillor Caterina in particular hammered away at this, suggesting that the City has accepted lower quality work because of mistakes made by the contractors. Pipe that was a smaller gauge than originally specified may have been accepted in exchange for some form of financial compensation, for instance.

The problem with that is any financial amount rendered today is likely far less than what it’ll cost if any work needs to be done in the future. I can envision the news now at a future Council update. There will be some sort of project that a future Council wants to implement, maybe running new cable to take advantage of some future technology, and they’ll be shocked when the price tag comes in significantly higher than expected because this pipe needs to be replaced with the appropriate gauge.

DSC_0803
Photo by Bill Burris

On the signalling contract, the City is holding back some of the payment until the work is done. The contract with Thales states the City can hold back 40%, which is about $19.8 million. Currently 49% of the contract has been paid. Responding to comments from Council that the amount is small to a big company, Farbrother said that “perhaps it’s not seen as punitive, but they are in the press every day” taking heat for the delay.

What these approaches don’t take into account is the wider impact of deficiencies and delays. What about all of the students and staff at NAIT who still can’t take the train? What about the numerous pedestrian and vehicular closures and detours that have added time to commutes and caused endless frustrations? What about the shattered confidence of the public in a year where we’ve had delays with nearly every major public project?

There’s too much in-camera & too little communication

City Council was scheduled to get an in-private update on the Metro Line yesterday. Thankfully, Mayor Iveson requested that the item be discussed in public instead. He wrote:

“Frankly, hearing yet another discussion of yet another private report does nothing to give the public confidence that this city council is getting information and in turn the public is getting information that we all need to determine what is going on with this project.”

“Too much of the discussion around this has been in private so I would like a public report and an opportunity for members of council to ask questions of Administration at least pertaining to these latest issues of deficiencies on the line, so there may be an airing of what is going on. At least any issues that can be clearly communicated to the public there is an opportunity to do that.”

While we didn’t come away with any major revelations during the update (aside from perhaps the number of reports commissioned on the construction) I think it’s critical that the discussion took place in public. Council did have a private update with Administration later in the day, but there’s no reason that everything needs to be done behind closed doors.

For one thing, Council desperately needs to restore the public’s faith in this project and going in-camera is not going to accomplish that. “The trust is gone, let’s just be honest about it,” said Councillor Nickel. “We need to restore people’s confidence,” said Councillor Sohi.

Kingsway/Royal Alex Station
Photo by Kurt Bauschardt

Unfortunately, it seems as though Administration’s first instinct is to go in-camera. For instance, when discussing the report on deficiencies, they attempted a few times to delay the discussion to the private session. “I’m a little disappointed that everything keeps getting reverted back to, ‘this is the normal course of construction’,” said Councillor Caterina. “At what point do we do something different?” asked Councillor Oshry, to which Administration replied, “That’s a perfect thing to discuss in private.”

This desire to go in-camera is a symptom of a much larger communications problem facing the City. Council was caught off-guard by Monday’s leaked report and is eager to prevent that from happening again. “Going forward, we’re going to want to know everything about everything,” Councillor Caterina told Administration.

To bring the discussion yesterday to a close, Mayor Iveson put forward a motion to have Administration “develop and immediately implement a public communication plan” and to prepare a report that outlines “any significant deficiencies with this project.”

“I want to be able to tell the public with confidence” that these issues “have been fully digested,” the mayor said. “The instinct to stop giving dates – we have to move past that, and just report on a regular basis,” he added. “We need to be zealous in our transparency and communication on this project.”

There doesn’t appear to be enough accountability

One thing lacking from the discussion yesterday was any accountability on the part of the City. Councillor McKeen and his colleagues did suggest a few times that the City and Council are ultimately responsible for public projects like this, but Administration seemed content to blame contractors. The public is calling for heads to roll, at least on Twitter, but there’s no sign that that is going to happen.

I’m reminded of that overused cliche about the definition of insanity. The Metro Line has been delayed again and again since December 2013, and yet the same people are in charge using the same contractors. If the inputs don’t change, how can we expect the outcomes to?

Clearly building an LRT line is a major endeavour and integrating it with an existing one has proven to be even more challenging. But it’s hard to reconcile that with the fact that so many other cities have successfully (from an outsider’s point-of-view) built even more complicated transit projects. That may not be a popular perspective within the city because it’s like comparing apples and oranges, but that’s absolutely what the public is thinking.

We’re 18 months past the first delay, and we still don’t have an opening date. How much farther down the current path do we go? We’ve heard from the City that changing contractors now and starting over on the signalling would be too costly, but that is beginning to sound an awful lot like the sunk cost fallacy. Maybe it would make more sense in the long-run to cut our losses and start over. We may not be paying Thales anything more, but we’re also not getting any closer to the end of the project.

I don’t think its wise to fire someone just to have a scapegoat, but it would go a long way toward restoring the public’s confidence in the City if some accountability measures were taken.

What impact does all of this have on the Valley Line LRT?

Understandably, Council had some questions yesterday about the impact of all of this on the Valley Line LRT. Councillor Sohi asked what, if anything, has been learned that could be applied to that project. The response? The importance of communication. Administration cited the establishment of five Citizen Working Groups as proof that things are improving with each project.

At one point, Wandzura tried to explain to Council that different procurement models result in different outcomes. The suggestion was that because the Valley Line will be built using a P3 model, we should expect things to be different. Different, yes. Better? Not necessarily. There are big concerns with the P3 model and the only reason we’re even going down that route is because it was the only way to secure federal funding. The Valley Line could very well turn out to be worse.

On the other hand, maybe expectations have been lowered so much with the Metro Line that the City will be able to exceed them with construction of the Valley Line.

When will we have an opening date for the Metro Line LRT?

Mayor Iveson asked yesterday if there’s any chance the line would be open by the start of school in the fall, to which Wandzura said he believed it would. Farbrother added that they didn’t want to suggest a date which could cause communications and public opinion to deteriorate even further. So the fall is City’s best guess, but at this point there’s no reason to have any faith in that time frame.

MacEwan Station & Rogers Place

As Paula Simons wrote, the stations and line look finished, yet they “just sit there, ghostly and pristine.” Right next door construction on Rogers Place continues, apparently on-time and on-budget. “Like a desert mirage, the promise of the NAIT LRT is always just out of reach,” Paula wrote. It’s looking increasingly likely that the new area will open before the Metro Line does.

In a private follow-up late yesterday afternoon, Council voted to hold a special meeting on the Metro Line LRT on August 17. They also made a private motion that “will move things forward” but of course we don’t know what that is just yet. An auditor’s report on the project is expected to be discussed by Council on August 24. That’s the most appropriate time for a retrospective, Farbrother suggested.

So for now we wait, with more questions than answers, and still without an opening date.

Metro Line LRT delayed again until Spring 2015, maybe, hopefully

The City held a press conference late this afternoon to provide an update on the Metro Line LRT extension to NAIT. They should have waited until February 2, because once again we learned that the opening of the new line has been delayed. The new target date is May 2015, more than a full year after the extension was originally slated to open.

2014-12-07 McEwan Station
MacEwan LRT Station in December 2014, photo by Darren Kirby

Today’s news release thanked Edmontonians for their patience and used much more careful language than previous delay announcements:

“Based on the most recent testing schedule provided by Thales Rail Signalling Solutions Inc., the City of Edmonton is cautiously optimistic the Metro Line LRT will open to public service in spring 2015.”

Cautiously optimistic is a long way from confident. The reason for the delay is the same thing we’ve heard since the project was first delayed – the contractor is having problems with the signaling system:

“Thales appreciates the patience of everyone in Edmonton as we work to complete the signaling system for the Metro Line,” says Thales Vice President Mario Peloquin. “We understand how important this essential transportation infrastructure is for the people of Edmonton, and we remain committed to delivering an outstanding product that is safe, efficient and reliable, and that will serve the city for generations to come.”

The signaling system is responsible for controlling train traffic. It tracks train movements and keeps them on schedule. Part of the challenge is that with the Metro Line, the City is changing the signaling system from a traditional fixed block system to a more modern communications-based train control system, or CBTC. It’s this new signaling system that will enable trains on the Metro and Capital lines to share the same tracks.

Even though construction completed on time and $90 million under budget, the Metro Line still isn’t open. The project has been delayed numerous times over the last year or so:

  • In September 2013, everything seemed on track for an April 2014 opening.
  • In December 2013, the opening was delayed a few months until Spring 2014.
  • In the Spring of 2014, the opening was further delayed until the end of the year. That schedule was reaffirmed over the summer.
  • In October 2014, the opening was delayed again, with February 2015 identified as the earliest possible date.
  • Now, in January 2015, the opening has been delayed until May 2015.

Needless to say, there’s very little confidence in the latest target date.

New Edmonton Arena Construction
MacEwan LRT Station next to the new downtown arena, September 2014

It was in October 2014 that Mayor Iveson called the delays “unacceptable” and asked the City Auditor to review how the project had been managed. Since then, the City has held back $20 million from the $55 million contract with Thales, and the auditor has been investigating.

Now the City says that the latest schedule from Thales would have the handover of the signaling system take place by March 23, 2015. If by some miracle Thales is actually able to meet that date, the City would need approximately 6 weeks to evaluate the system and complete staff training.

“We are very concerned with the ongoing delay of the Metro Line and will continue doing everything we can to hold Thales to their new schedule. Our goal remains the same: to open the Metro Line for safe, reliable public service as quickly as possible.”

On the Metro Line LRT site, the City has made available a slide deck and an FAQ, both in PDF.

metro line delayed

The FAQ tries to explain what has happened and attempts to provide some confidence that the City is providing “increased” project oversight to ensure it gets done. After the number of delays this project has experienced, you have to wonder if sticking with Thales is the right approach, but that’s what the City is doing:

“At present, our best option is to continue supporting Thales to deliver the signaling system. Our expectation is that Thales will meet its commitments. The City has strict project oversight to ensure they do so. If they fail to meet a milestone or if testing does not proceed according to schedule, the City will hold Thales to account.”

Let’s hope the sunk cost fallacy isn’t at play here.

The City says they are “tracking milestones on a daily basis” and have increased resources on the project. “We’re working diligently to help Thales deliver the signaling system by March 23, 2015.” The FAQ even says the City has explored the option of using people to manage train movements in an effort to get the new line open more quickly, but they ultimately decided that approach did not meet requirements for cost, safety, reliability, or efficiency.

Curiously, the final question in the FAQ is, “are you feeling badly about the delay, City of Edmonton?” Here’s the answer:

“Everyone involved with the Metro Line project regrets the delay of this exciting transportation project. We ask for your patience and hope you’ll continue to bear with us as we work towards bringing the Metro Line into service in spring 2015.”

So we’ll have to wait until late March before we can be sure the Spring 2015 opening is actually going to happen. In the meantime, we’d better make sure the same problems aren’t going to plague the Valley Line LRT extension.